Doubtnut Promotions Sticky

6 men can complete the electric fitting in a building in 7 days. How many days will it take if 21 men do the job?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

6 men can complete the work in =7 days
1 man will complete the same work in
=76 days
(Less men, more days)
21 men will finish the work in
=7621 days
(More men, less days)
=2 days.

|
Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    12 men and 16 women can complete a jon in 5 days. 13 men and 24 women can complete the same job in 4 days. How long, in days, will 5 men and 10 women take to complete the same job?

    A5
    B12
    C10
    D15
  • Question 1 - Select One

    7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?

    A28
    B21
    C14
    D7
  • Question 1 - Select One

    22 men can complete a job in 16days. In how many days, will 32 men complete that job?

    A14
    B12
    C16
    D11
  • Question 1 - Select One

    34 men can do a piece of work in 12 days . How many days will 51 men take to do it

    Aa) 8
    Bb) 5
    Cc) 10
    Dd) 6
  • Question 1 - Select One

    45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?

    A10
    B16
    C18
    D15
  • Question 1 - Select One

    7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work

    A28
    B21
    C14
    D7
  • Question 1 - Select One

    15 men can do a work in 20 days. How many days will 10 men take to do double the same work0

    A40
    B60
    C50
    D30

Similar Questions