Doubtnut Promotions Sticky

A and B can do a piece of work in 6 days and 4 days respectively. A started the work, worked at it for 2 days and then was joined by B. Find the total time taken to complete the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

"A′s 1 day work =16
B′s 1 day work =14
Aand B 1 day work=14+16
=512 A's 2 days work=2×16'
=13
Remaining work =113='23
∵(whole work =1)
Now A and B can do 512 th work in 1 day
They will do 1 work (Whole work) in 1×125 days
And they will do 23th of 1 work =125×23=85 days
∴ Total work was finished in =85+2
=185 days."

|
Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 1 - Select One

    A and B can do a piece of work in 20 days and 12 days respectively. A started the work alone and then after 4 days B joined him till the completion of the work. How long did the work last?

    A10 days
    B20 days
    C15 days
    D6 days
  • Question 1 - Select One

    A and B can do a piece of work in 6 and 12 days, respectively. They (both) will complete the work in how many days?

    A9 days
    B18 days
    C6 days
    D4 days
  • Question 1 - Select One

    A and B can do a piece of work in 30 days and 18 days respectively. A started the work alone and then after 6 days B joined him till the completion of the work. In how many days has the whole work completed?
    A और B क्रमशः किसी काम को 30 दिन और 18 दिन में पूरा करते है | A किसी काम को अकेले शुरू करता है और छह दिन बाद B उसके साथ काम खत्म होने तक काम करता है | पूरा काम कितने दिन में खत्म होगा ?

    A12
    B9
    C15
    D17
  • Question 1 - Select One

    A and B can do a piece of work in 24 and 30 days respectively.
    Both started the work and worked for 6 days. Then B leaves
    the work and C joins and the remaining work is completed by A and C together in 11 days. Find the days in which C
    alone can do the work

    A80
    B100
    C120
    D130

Similar Questions