Doubtnut Promotions Sticky

A takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is

A

15

B

12

C

10

D

9

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C

|
Answer

Step by step video, text & image solution for A takes 5 hours more time than that taken by B to complete a work. If working together they can complete a work in 6 hours, then the number of hours that takes to complete the work individually is by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Related Playlists


Similar Practice Problems

  • Question 1 - Select One

    6 women can complete a work in 46 hours. In how many hours will 23 women complete that work?

    A18
    B16
    C12
    D24
  • Question 1 - Select One

    If 40 men working 12 hours a day can complete a work in 8 days, then how many men working 4 hours a day can complete the same work in 16 days ?
    यदि 40 लोग प्रतिदिन 12 घंटे कार्य करके किसी कार्य को 8 दिनों में समाप्त कर सकते हैं, तो इस कार्य को प्रतिदिन 4 घंटे कार्य करते हुए 16 दिनों में समाप्त करने के लिए कितने पुरुषों की आवश्यकता होगी ?

    A50
    B60
    C54
    D45
  • Question 1 - Select One

    A can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?

    A8
    B3
    C4
    D6
  • Question 1 - Select One

    B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?

    A30
    B15
    C20
    D10
  • Question 1 - Select One

    B would have taken 10 hours more than what A would have taken to complete a task if each of them worked alone. Working together they can complete the task in 12 hours. How many hours would B take to do 50% of the task?

    A30
    B15
    C20
    D10

Similar Questions