Doubtnut Promotions Sticky

Rohan can paint 1/3 of a painting in 6 days. How many days will he take to complete the painting?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Given
Rohan can paint13 of the paint in 6 days
Time taken by rohan to complete the painting is (6×3) days = 18 days

|
Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • Question 1 - Select One

    A can complete a work in 'm' days and B can complete it in 'n' days. How many days will it take to complete the work if both A and B work together?

    A(m+n) days
    B(1m×1n) days
    C(m+nmn) days
    D(mnm+n) days
  • Question 1 - Select One

    A company has a job to prepare certain number cans and there are three machines A, B and C for this job. A can complete the job in 3 days, B can complete the job in 4 days, and C can complete the job in 6 days. How many days will the company take to complete the job if all the machines are used simultaneously?

    A4/3 days
    B3 days
    C3 days
    D12 days
  • Question 1 - Select One

    A and B together can complete a particular task in 8 days. If
    B alone can complete the same task in 10 days, how many
    days will A take to complete the task if he works alone ?

    A28
    B36
    C40
    D32
  • Question 1 - Select One

    12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?

    A2
    B3
    C4
    D412
  • Question 1 - Select One

    Three men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?

    A1 days
    B2 days
    C3 days
    D4 days
  • Question 1 - Select One

    Rohan and Mohit together can build a wall in 8 days. Mohit and Vikas can build the same wall in 10 days and Vikas and Rohan can build the same wall in 12 days. In how many days can all the three complete the same wall while working together?

    A24037
    B12037
    C15037
    D18037
  • Question 1 - Select One

    Rohan and Mohit together can build a wall in 8 days. Mohit and Vikas can build the same wall in 10 days and Vikas and Rohan can build the same wall in 12 days. In how many days can all the three complete the same wall while working together?

    A240/37
    B120/37
    C150/37
    D180/37

Similar Questions