To complete a piece of work A takes 50% more time than B. If together they take 18 days to complete the work how much time will B take to do it? a 30 days b 35 days c 40 days d 45 days
Correct option a 30 days Explanation: efficiency of work = 2 : 3 Time and efficiency inversely proportion to each otherTotal work = 18days ×2+3 unit = 90 unitB Completes the work
Related Solutions
A can do a piece of work in 40 days. He works for 5 days and B completes the remaining work in 2.1 days. If both A and B together do the work, then in how much time will it take to complete it?
View SolutionA takes 5 days more than B and 9 days more than C to complete a work. C works as much as (A + B) works together. In how many days will B and C together complete this work ?
View SolutionTo complete a work, A takes 50% more time than B. If together they take 18 days to complete the work, how much time shall B take to do it ?
View SolutionTo complete a wall, X takes 20% more time than Y. If together they complete the wall in 30 days, how much time (in days) will Y alone take to complete it?
View SolutionA takes days more than (A + B) together to complete a work. B takes 8 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 27 days more than (A + B) together to complete a work. B takes 3 days more than (A + B) together to complete a work. In how many days will (A + B) complete this work ?
View SolutionA takes 24 days more than B and 32 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
View SolutionA takes 7 days more than B and 16 days more than C to complete a work. C works as much as (A + B) works together. In how many days will A, B and C alone complete this work ?
View SolutionA can complete a work in 18 days, B in 20 days and C in 30 days. B and C together start the work but after 2 days, they left the work. How many days will a take to complete the remaining work ?
View SolutionA alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?
View SolutionA is twice as efficient as B and together they finish a piece of work in 18 days. How many days will A take to complete the work alone?
View SolutionA and B can do a piece of work in 30 days, B and C can do it in 40 days, while C and A can do it in 60 days. How long will it take to complete all the three work together?
View SolutionA is 1.5 times as efficient as B, so he takes 8 days less than B to complete a piece of work. A and B work on alternate days and A does the work on the first day, then in how many days will the work be completed?
View SolutionB works four times as much as A. If B takes 15 days less than A to complete this work. In how many days will A and B alone complete this work ?
View SolutionA takes 24 days more than B and 32 days more than C to do a piece of work. Alone does as much work as A and B together. Then in how many days will A, B and C do it separately?
View SolutionA, B and C can do a piece of work in 12, 18 and 36 days respectively. They all work together for 2 days and then B leaves. How much time will A and C take to complete the work?
View SolutionA is thrice as efficient as B, so A takes 40 days less than the number of days B takes to complete a piece of work. In how many days will both of them together complete the work?
View SolutionA can do a piece of work in certain number of days, while B takes three days more than A to complete the same work. Working together, A and B can complete the work in two days. How many days does B take to complete the work?
View SolutionA can do a piece of work in 24 days, B in 9 days and C in 12 days. B and C start the work together, but leave after 3 days. How many days will A take to complete the remaining work?
View SolutionAcan do a work in 6 days and B in 9 days. How many days will both take together to complete the work?
View Solution