12 man complete a work in 18 days they start but after 6 days four more man join the work. How many days will take all the man to complete the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

12 man complete work in 18 days
1 man complete work in 18*12 days
1 days work 11812
upto 6 days ->12
12 man 1 days work =1181212=118
12 man, 6 days=1186=13
Remaining work =2/3
Now, total man=16
1 man 1 day work=11812
16 man 1 day work=161812
Let then take x days to complete 2/3 work
161812x=23
x=9 days
6 days in 12 men
9 days in 16 women
total 15 days .

Updated on:21/07/2023
|


Similar Questions


Knowledge Check

  • 12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?

    A10 days
    B12 days
    C15 days
    D9 days
  • 14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?

    A9 days
    B5 days
    C6 days
    D7 days
  • 18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
    18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?

    A3
    B212
    C2
    D312