12 man complete a work in 18 days they start but after 6 days four more man join the work. How many days will take all the man to complete the work.
12 man complete work in 18 days
1 man complete work in 18*12 days
1 days work 118⋅12
upto 6 days ->12
12 man 1 days work =118⋅12⋅12=118
12 man, 6 days=118⋅6=13
Remaining work =2/3
Now, total man=16
1 man 1 day work=118⋅12
16 man 1 day work=1618⋅12
Let then take x days to complete 2/3 work
1618⋅12⋅x=23
x=9 days
6 days in 12 men
9 days in 16 women
total 15 days .
Similar Questions
45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View Solution45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution
Knowledge Check
12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
A10 daysB12 daysC15 daysD9 days14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
A9 daysB5 daysC6 daysD7 days18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?A3B212C2D312
Twelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionP can complete a work in 15 days.Q can complete the same work in 10 days ,P started working and after 5 days Q joined him. How many days more will they take to complete the remaining work ?
View Solution