Vijay is 10% more efficient than Vikas. If Vikas can complete a piece of work in 33 days. Then Vijay can complete the same work in how many days ?
25
27
30
36
The correct Answer is:C
To solve the problem step by step, we will analyze the efficiencies of Vijay and Vikas, and then calculate the time taken by Vijay to complete the same work.
Step 1: Understand the relationship between Vijay and Vikas's efficiencies.
Vijay is 10% more efficient than Vikas. If we assume Vikas's efficiency is 100 units of work per day, then Vijay's efficiency can be calculated as:
Vijay's Efficiency=Vikas's Efficiency+10% of Vikas's Efficiency
Vijay's Efficiency=100+10=110 units of work per day
Step 2: Calculate Vikas's efficiency.
Since Vikas can complete the work in 33 days, we can calculate the total work done by Vikas:
Total Work=Vikas's Efficiency×Time taken by Vikas
Total Work=100×33=3300 units of work
Step 3: Calculate the time taken by Vijay to complete the same work.
Now, we will use Vijay's efficiency to find out how many days he will take to complete the same total work:
Time taken by Vijay=Total WorkVijay's Efficiency
Time taken by Vijay=3300110=30 days
Final Answer:
Vijay can complete the same work in 30 days.
---
Vijay is 10% more efficient than Vikas. If we assume Vikas's efficiency is 100 units of work per day, then Vijay's efficiency can be calculated as:
Vijay's Efficiency=Vikas's Efficiency+10% of Vikas's Efficiency
Vijay's Efficiency=100+10=110 units of work per day
Since Vikas can complete the work in 33 days, we can calculate the total work done by Vikas:
Total Work=Vikas's Efficiency×Time taken by Vikas
Total Work=100×33=3300 units of work
Now, we will use Vijay's efficiency to find out how many days he will take to complete the same total work:
Time taken by Vijay=Total WorkVijay's Efficiency
Time taken by Vijay=3300110=30 days
Vijay can complete the same work in 30 days.
Similar Questions
Knowledge Check
- Question 1 - Select One
A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
A10B12C14D15 - Question 2 - Select One
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
A10B12C14D16 - Question 3 - Select One
Raman is 25% more efficient than Aman. If Aman can complete a piece of work in 25 days, then Raman can complete the same work in how many days?
A12B15C16D20
A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View SolutionShivam is 10% less efficient than Vivek. If Vivek can make a helmet in 9 days, then in how many days Shivam can complete the same work?
View Solution21 men can complete a piece of work in 427 days. In how many days can 18 men complete the same piece of work?
View SolutionP, Q and R together can complete a work in 40 days. P and Q together can complete the same work in 90 days. Then R alone can complete the same work in how many days?
View Solution