Lokesh starts a work and after 6 days he left and remaining work finished by Rakesh in 12 days. Had Lokesh worked for 9 days, Rakesh would have finished the remaining work in 8 days. Find the time taken by Lokesh to complete the work alone.
12 days
9 days
15 days
18 days
The correct Answer is:C
To solve the problem step by step, we will denote Lokesh's efficiency as L and Rakesh's efficiency as R.
Step 1: Understand the Work Done
Lokesh works for 6 days and then Rakesh completes the remaining work in 12 days. We can express the total work in terms of their efficiencies.
Step 2: Set Up the Equations
From the first condition:
- Work done by Lokesh in 6 days = 6L
- Work done by Rakesh in 12 days = 12R
The total work can be expressed as:
6L+12R=Total Work(1)
Step 3: Analyze the Second Condition
If Lokesh had worked for 9 days, Rakesh would have finished the remaining work in 8 days.
- Work done by Lokesh in 9 days = 9L
- Remaining work done by Rakesh in 8 days = 8R
The total work can also be expressed as:
9L+8R=Total Work(2)
Step 4: Equate the Total Work from Both Conditions
From equations (1) and (2), we can set them equal to each other:
6L+12R=9L+8R
Step 5: Rearranging the Equation
Rearranging gives:
12R−8R=9L−6L
4R=3L
Step 6: Find the Ratio of Efficiencies
From the equation 4R=3L, we can express the ratio of Lokesh's efficiency to Rakesh's efficiency:
LR=43
Step 7: Express Rakesh's Efficiency in Terms of Lokesh's
Let R=34L.
Step 8: Substitute Back to Find Total Work
Substituting R in either equation (1) or (2) to find the total work. Let's use equation (1):
6L+12(34L)=Total Work
6L+9L=Total Work
15L=Total Work
Step 9: Calculate the Time Taken by Lokesh Alone
To find the time taken by Lokesh to complete the work alone, we use:
Time=Total WorkEfficiency of Lokesh=15LL=15 days
Final Answer
Thus, the time taken by Lokesh to complete the work alone is 15 days.
Lokesh works for 6 days and then Rakesh completes the remaining work in 12 days. We can express the total work in terms of their efficiencies.
From the first condition:
- Work done by Lokesh in 6 days = 6L
- Work done by Rakesh in 12 days = 12R
6L+12R=Total Work(1)
If Lokesh had worked for 9 days, Rakesh would have finished the remaining work in 8 days.
- Work done by Lokesh in 9 days = 9L
- Remaining work done by Rakesh in 8 days = 8R
9L+8R=Total Work(2)
From equations (1) and (2), we can set them equal to each other:
6L+12R=9L+8R
Rearranging gives:
12R−8R=9L−6L
4R=3L
From the equation 4R=3L, we can express the ratio of Lokesh's efficiency to Rakesh's efficiency:
LR=43
Let R=34L.
Substituting R in either equation (1) or (2) to find the total work. Let's use equation (1):
6L+12(34L)=Total Work
6L+9L=Total Work
15L=Total Work
To find the time taken by Lokesh to complete the work alone, we use:
Time=Total WorkEfficiency of Lokesh=15LL=15 days
Thus, the time taken by Lokesh to complete the work alone is 15 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS
55 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS
15 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? a. 2.5 days, 7.5 days b. 5 days, 8.5 days c. 5 days, 15 days d. none of these
View SolutionA started a work and left after working for 4 days, then B was called and he finished the work in 18 days. If A left the work after working for 6 days then B would have finished the remaining work in 12 days. In how many days can each of them, working alone finish the whole work?
View Solution
Knowledge Check
A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in
A16 daysB24 daysC28 daysD29 daysA can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?
A60B55C75D70A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
A3 daysB5 daysC7 daysD11 days
A can do a piece of work in 80 days.He works at it for 10 days and then B alore finishes the remaining work in 42 days.How long will B take to do the entire work alone?
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View SolutionArjun started a task and left it after working for 2 days. Then, Bharath was called and he completed the task in 9 days. If Arjun alone had worked for 3 days, Bharath alone would have finished the remaining work in 6 days. In how many days can Arjun alone complete the task?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA can do a piece of work in 60 days. He works for 15 days and then B alone finishes the remaining work in 30 days. The two together can finish the work in
View Solution