Doubtnut Promotions Sticky

Lokesh starts a work and after 6 days he left and remaining work finished by Rakesh in 12 days. Had Lokesh worked for 9 days, Rakesh would have finished the remaining work in 8 days. Find the time taken by Lokesh to complete the work alone.

A

12 days

B

9 days

C

15 days

D

18 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will denote Lokesh's efficiency as L and Rakesh's efficiency as R.

Step 1: Understand the Work Done
Lokesh works for 6 days and then Rakesh completes the remaining work in 12 days. We can express the total work in terms of their efficiencies.

Step 2: Set Up the Equations
From the first condition:
- Work done by Lokesh in 6 days = 6L
- Work done by Rakesh in 12 days = 12R

The total work can be expressed as:
6L+12R=Total Work(1)

Step 3: Analyze the Second Condition
If Lokesh had worked for 9 days, Rakesh would have finished the remaining work in 8 days.
- Work done by Lokesh in 9 days = 9L
- Remaining work done by Rakesh in 8 days = 8R

The total work can also be expressed as:
9L+8R=Total Work(2)

Step 4: Equate the Total Work from Both Conditions
From equations (1) and (2), we can set them equal to each other:
6L+12R=9L+8R

Step 5: Rearranging the Equation
Rearranging gives:
12R8R=9L6L
4R=3L

Step 6: Find the Ratio of Efficiencies
From the equation 4R=3L, we can express the ratio of Lokesh's efficiency to Rakesh's efficiency:
LR=43

Step 7: Express Rakesh's Efficiency in Terms of Lokesh's
Let R=34L.

Step 8: Substitute Back to Find Total Work
Substituting R in either equation (1) or (2) to find the total work. Let's use equation (1):
6L+12(34L)=Total Work
6L+9L=Total Work
15L=Total Work

Step 9: Calculate the Time Taken by Lokesh Alone
To find the time taken by Lokesh to complete the work alone, we use:
Time=Total WorkEfficiency of Lokesh=15LL=15 days

Final Answer
Thus, the time taken by Lokesh to complete the work alone is 15 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A can do a piece of work in 18 days. He worked at it for 12 days and B finished the remaining work in 8 days. B alone can do the whole work in

    A16 days
    B24 days
    C28 days
    D29 days
  • Question 2 - Select One

    A can do a piece of work in 30 days. He worked for 6 days and B finished the remaining work in 48 days. B alone can do the whole work in how many days?

    A60
    B55
    C75
    D70
  • Question 3 - Select One

    A can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in

    A3 days
    B5 days
    C7 days
    D11 days