Doubtnut Promotions Sticky

A certain job was assigned to a group of men to do it in 24 days. But 14 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was

A

A)32

B

B)66

C

C)36

D

D)56

Video Solution
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for A certain job was assigned to a group of men to do it in 24 days. But 14 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A certain job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and the remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 2 - Select One

    A certain-job was assigned to a group of men to do in 20 days. But 12 men did not turn up for the job and remaining men did the job in 32 days. The original number of men in the group was :

    A32
    B36
    C42
    D40
  • Question 3 - Select One

    Some carpenters promised to do a job in 9 days but 5 of them were absent and remaining men did the job in 12 days. The original number of carpenters was

    A24
    B20
    C16
    D18