Doubtnut Promotions Sticky

15 men can complete a work in 8 days while 10 women can complete the same work in 20 days. 7 men starts working and after 12 days they are replaced by 10 women. Find time taken by 10 women to complete the remaining work.

A

A)5 days

B

B)8 days

C

C)7 days

D

D)6 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will follow these steps:

Step 1: Calculate the total work done by men and women.
1. Men's Work Rate:
- 15 men can complete the work in 8 days.
- Therefore, the total work can be calculated as:
Total Work=Number of Men×Days=15×8=120 man-days

2. Women's Work Rate:
- 10 women can complete the same work in 20 days.
- Therefore, the total work can also be calculated as:
Total Work=Number of Women×Days=10×20=200 woman-days

Step 2: Find the work done by 7 men in 12 days.
1. Efficiency of 1 Man:
- Since 15 men can complete the work in 120 man-days, the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=1120 of the work

2. Efficiency of 7 Men:
- Therefore, the work done by 7 men in 1 day is:
Work done by 7 men in 1 day=7×1120=7120

3. Work done by 7 Men in 12 Days:
- The total work done by 7 men in 12 days is:
Total work done=12×7120=84120=710 of the work

Step 3: Calculate the remaining work.
1. Remaining Work:
- If 7 men completed 710 of the work, the remaining work is:
Remaining Work=1710=310 of the work

Step 4: Calculate the time taken by 10 women to complete the remaining work.
1. Efficiency of 10 Women:
- From the previous calculations, we know that 10 women can complete the work in 200 woman-days.
- Therefore, the work done by 1 woman in 1 day is:
Work done by 1 woman in 1 day=1200
- Thus, the work done by 10 women in 1 day is:
Work done by 10 women in 1 day=10×1200=10200=120

2. Time Taken by 10 Women to Complete Remaining Work:
- To find the time taken T by 10 women to complete 310 of the work:
120×T=310
- Solving for T:
T=310×20=6 days

Final Answer:
The time taken by 10 women to complete the remaining work is 6 days.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32
  • Question 2 - Select One

    12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?

    A16
    B12
    C18
    D10
  • Question 3 - Select One

    15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?

    A10 days
    B8 days
    C12 days
    D9 days