15 men can complete a work in 8 days while 10 women can complete the same work in 20 days. 7 men starts working and after 12 days they are replaced by 10 women. Find time taken by 10 women to complete the remaining work.
A)5 days
B)8 days
C)7 days
D)6 days
The correct Answer is:D
To solve the problem step by step, we will follow these steps:
Step 1: Calculate the total work done by men and women.
1. Men's Work Rate:
- 15 men can complete the work in 8 days.
- Therefore, the total work can be calculated as:
Total Work=Number of Men×Days=15×8=120 man-days
2. Women's Work Rate:
- 10 women can complete the same work in 20 days.
- Therefore, the total work can also be calculated as:
Total Work=Number of Women×Days=10×20=200 woman-days
Step 2: Find the work done by 7 men in 12 days.
1. Efficiency of 1 Man:
- Since 15 men can complete the work in 120 man-days, the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=1120 of the work
2. Efficiency of 7 Men:
- Therefore, the work done by 7 men in 1 day is:
Work done by 7 men in 1 day=7×1120=7120
3. Work done by 7 Men in 12 Days:
- The total work done by 7 men in 12 days is:
Total work done=12×7120=84120=710 of the work
Step 3: Calculate the remaining work.
1. Remaining Work:
- If 7 men completed 710 of the work, the remaining work is:
Remaining Work=1−710=310 of the work
Step 4: Calculate the time taken by 10 women to complete the remaining work.
1. Efficiency of 10 Women:
- From the previous calculations, we know that 10 women can complete the work in 200 woman-days.
- Therefore, the work done by 1 woman in 1 day is:
Work done by 1 woman in 1 day=1200
- Thus, the work done by 10 women in 1 day is:
Work done by 10 women in 1 day=10×1200=10200=120
2. Time Taken by 10 Women to Complete Remaining Work:
- To find the time taken T by 10 women to complete 310 of the work:
120×T=310
- Solving for T:
T=310×20=6 days
Final Answer:
The time taken by 10 women to complete the remaining work is 6 days.
---
1. Men's Work Rate:
- 15 men can complete the work in 8 days.
- Therefore, the total work can be calculated as:
Total Work=Number of Men×Days=15×8=120 man-days
- 10 women can complete the same work in 20 days.
- Therefore, the total work can also be calculated as:
Total Work=Number of Women×Days=10×20=200 woman-days
1. Efficiency of 1 Man:
- Since 15 men can complete the work in 120 man-days, the work done by 1 man in 1 day is:
Work done by 1 man in 1 day=1120 of the work
- Therefore, the work done by 7 men in 1 day is:
Work done by 7 men in 1 day=7×1120=7120
- The total work done by 7 men in 12 days is:
Total work done=12×7120=84120=710 of the work
1. Remaining Work:
- If 7 men completed 710 of the work, the remaining work is:
Remaining Work=1−710=310 of the work
1. Efficiency of 10 Women:
- From the previous calculations, we know that 10 women can complete the work in 200 woman-days.
- Therefore, the work done by 1 woman in 1 day is:
Work done by 1 woman in 1 day=1200
- Thus, the work done by 10 women in 1 day is:
Work done by 10 women in 1 day=10×1200=10200=120
- To find the time taken T by 10 women to complete 310 of the work:
120×T=310
- Solving for T:
T=310×20=6 days
The time taken by 10 women to complete the remaining work is 6 days.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start’ working on the job and after working for 2 days, all of them stopped working. How many women should be put on the job to Complete the remaining work, if it is to be completed in 3 days?
View Solution12 men can complete a piece of work in 4 days, while 15 women can complete the same work in 4 days. 6 men start working on the job and after working for two days, all of them stopped working. How many women should be put on the job to complete the remaining work, if It is to be completed in 3 days
View Solution
Knowledge Check
- Question 1 - Select One
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D32 - Question 2 - Select One
12 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
A16B12C18D10 - Question 3 - Select One
15 men can complete a work in 10 days while 20 boys can complete the same work in 15 days How many days will 10 men and 10 boys together take to complete the same work ?
A10 daysB8 daysC12 daysD9 days
24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution5 men can do a work in 6 days and 10 women can do the same work in 5 days. In how many days the work is done by 5 women and 3 men?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View Solution