Doubtnut Promotions Sticky

A & B can do a piece of work together in 24 days and C's efficiency is half of A's efficiency. If all three work together, they can complete the same work in 20 days, then find how many days are required to complete the work, if B and C work together?

A

A)45 days

B

B)42 days

C

C)30 days

D

D)48 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, let's break it down step by step.

Step 1: Determine the work done by A and B together.
A and B can complete the work together in 24 days. This means their combined work rate (efficiency) is:
Efficiency of A and B=1 work24 days=124 work/day

Step 2: Calculate the total work in terms of units.
If we consider the total work to be 120 units (a common multiple of 24 and 20 for easier calculations), then:
Total Work=120 units

Step 3: Find the efficiency of A and B.
Since A and B can complete 120 units of work in 24 days, their combined efficiency in units is:
Efficiency of A and B=120 units24 days=5 units/day

Step 4: Determine the efficiency of A, B, and C together.
A, B, and C can complete the same work in 20 days, so their combined efficiency is:
Efficiency of A, B, and C=120 units20 days=6 units/day

Step 5: Calculate the efficiency of C.
From the efficiencies calculated:
Efficiency of C=Efficiency of A, B, and CEfficiency of A and B=65=1 unit/day

Step 6: Relate C's efficiency to A's efficiency.
According to the problem, C's efficiency is half of A's efficiency. Let A's efficiency be x:
Efficiency of C=x2
We found that C's efficiency is 1 unit/day, so:
x2=1x=2 units/day
Thus, A's efficiency is 2 units/day.

Step 7: Find B's efficiency.
Since A and B together have an efficiency of 5 units/day:
Efficiency of B=5Efficiency of A=52=3 units/day

Step 8: Calculate the efficiency of B and C together.
Now we can find the combined efficiency of B and C:
Efficiency of B and C=Efficiency of B+Efficiency of C=3+1=4 units/day

Step 9: Calculate the time taken by B and C to complete the work.
The time taken by B and C to complete 120 units of work is:
Time=Total WorkEfficiency of B and C=120 units4 units/day=30 days

Final Answer:
B and C together will take 30 days to complete the work.

---

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?

    A60 days
    B45 days
    C40 days
    D30 days
  • Question 2 - Select One

    A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.

    A36
    B18
    C48
    D30
  • Question 3 - Select One

    If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
    (a)60 days
    (b) 50 days
    (c)30 days
    (d)40 days

    A60 days
    B50 days
    C30 days
    D40 days