A & B can do a piece of work together in 24 days and C's efficiency is half of A's efficiency. If all three work together, they can complete the same work in 20 days, then find how many days are required to complete the work, if B and C work together?
A)45 days
B)42 days
C)30 days
D)48 days
The correct Answer is:C
To solve the problem, let's break it down step by step.
Step 1: Determine the work done by A and B together.
A and B can complete the work together in 24 days. This means their combined work rate (efficiency) is:
Efficiency of A and B=1 work24 days=124 work/day
Step 2: Calculate the total work in terms of units.
If we consider the total work to be 120 units (a common multiple of 24 and 20 for easier calculations), then:
Total Work=120 units
Step 3: Find the efficiency of A and B.
Since A and B can complete 120 units of work in 24 days, their combined efficiency in units is:
Efficiency of A and B=120 units24 days=5 units/day
Step 4: Determine the efficiency of A, B, and C together.
A, B, and C can complete the same work in 20 days, so their combined efficiency is:
Efficiency of A, B, and C=120 units20 days=6 units/day
Step 5: Calculate the efficiency of C.
From the efficiencies calculated:
Efficiency of C=Efficiency of A, B, and C−Efficiency of A and B=6−5=1 unit/day
Step 6: Relate C's efficiency to A's efficiency.
According to the problem, C's efficiency is half of A's efficiency. Let A's efficiency be x:
Efficiency of C=x2
We found that C's efficiency is 1 unit/day, so:
x2=1⟹x=2 units/day
Thus, A's efficiency is 2 units/day.
Step 7: Find B's efficiency.
Since A and B together have an efficiency of 5 units/day:
Efficiency of B=5−Efficiency of A=5−2=3 units/day
Step 8: Calculate the efficiency of B and C together.
Now we can find the combined efficiency of B and C:
Efficiency of B and C=Efficiency of B+Efficiency of C=3+1=4 units/day
Step 9: Calculate the time taken by B and C to complete the work.
The time taken by B and C to complete 120 units of work is:
Time=Total WorkEfficiency of B and C=120 units4 units/day=30 days
Final Answer:
B and C together will take 30 days to complete the work.
---
A and B can complete the work together in 24 days. This means their combined work rate (efficiency) is:
Efficiency of A and B=1 work24 days=124 work/day
If we consider the total work to be 120 units (a common multiple of 24 and 20 for easier calculations), then:
Total Work=120 units
Since A and B can complete 120 units of work in 24 days, their combined efficiency in units is:
Efficiency of A and B=120 units24 days=5 units/day
A, B, and C can complete the same work in 20 days, so their combined efficiency is:
Efficiency of A, B, and C=120 units20 days=6 units/day
From the efficiencies calculated:
Efficiency of C=Efficiency of A, B, and C−Efficiency of A and B=6−5=1 unit/day
According to the problem, C's efficiency is half of A's efficiency. Let A's efficiency be x:
Efficiency of C=x2
We found that C's efficiency is 1 unit/day, so:
x2=1⟹x=2 units/day
Thus, A's efficiency is 2 units/day.
Since A and B together have an efficiency of 5 units/day:
Efficiency of B=5−Efficiency of A=5−2=3 units/day
Now we can find the combined efficiency of B and C:
Efficiency of B and C=Efficiency of B+Efficiency of C=3+1=4 units/day
The time taken by B and C to complete 120 units of work is:
Time=Total WorkEfficiency of B and C=120 units4 units/day=30 days
B and C together will take 30 days to complete the work.
Topper's Solved these Questions
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)40videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - MAINS QUESTIONS55videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - BASIC QUESTIONS15videos
TIME AND WORK & PIPE AND CISTERN
- BOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions31videos
SPEED, TIME AND DISTANCE
Similar Questions
Knowledge Check
- Question 1 - Select One
If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?
A60 daysB45 daysC40 daysD30 days - Question 2 - Select One
A is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
A36B18C48D30 - Question 3 - Select One
If A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
(a)60 days
(b) 50 days
(c)30 days
(d)40 daysA60 daysB50 daysC30 daysD40 days
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionA can do a piece of work in 9 days, In how many days can the work be completed if A and B work together ?
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View SolutionA is twice as efficient as B and they together can complete a piece of work in 24 days. Find the number of days, that A alone takes to compelete the work.
View Solution