12 men can finish a project in 20 days. 18 women can finish
the same project in 16 days and 24 children can finish it in 18
days. 8 women and 16 children worked for 9 days and then
left. In how many will 10 men coplete the remaining project ?
1012
10
9
1112
The correct Answer is:(b)
=(12×200M=(18×16)W=(24×18)C
or, 240M=288W=432C
or,5M=6W=9C
Work done by 8 women and 16 children in 9 days
=(406M+809M)×9=(120M+160M18)×9=140M<br>thereforeRema∈∈gwork<br>= 12 M xx 20 - 140 M<br>= 240 M - 140 = 100M<br>therefore 10mencancomp≤teti∈<br>=100/10 = 10 days
Related Playlists
Similar Questions
If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.
View Solution6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
View Solution6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
View Solution10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?
View Solution2 men can complete a piece of work in 6 days. 2 women can
complete the same piece of work in 9 days. Where as 3
children can complete the same piece of work in 8 days. 3
women and 4 children worked together for 1 day. If only
men were to finish the remaining work in day, how many
total men would be required?View SolutionIf 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
View Solution