150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.Solution in Telugu
Step by step video & image solution for 150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Updated on:21/07/2023Topper's Solved these Questions
- PROGRESSIONSBOOK - VGS PUBLICATION-BRILLIANTCHAPTER - PROGRESSIONSEXERCISE - Creative Bits for CCE Model Examination
129 Videos
- PROBABILITY (MULTIPLE CHOICE QUESTION)BOOK - VGS PUBLICATION-BRILLIANTCHAPTER - PROBABILITY (MULTIPLE CHOICE QUESTION)EXERCISE - PROBABILITY (MULTIPLE CHOICE QUESTION)
20 Videos
- PROGRESSIONS (MULTIPLE CHOICE QUESTION)BOOK - VGS PUBLICATION-BRILLIANTCHAPTER - PROGRESSIONS (MULTIPLE CHOICE QUESTION)EXERCISE - PROGRESSIONS (MULTIPLE CHOICE QUESTION)
20 Videos
Similar Questions
How many terms of A.P. −6,−112,−5 …… are needed to obtain a sum -25?
View SolutionThe probability that a leap year will have 52 tuesdays is………..
View SolutionA circle with area A, is contained in the interior of a larger with area A1+A2. IF the radius of the larger circle is 3 units and A1,A2 and (A1+A2) are in A.P., then find the radius of smaller circle…..
View Solution150 workers were engaged to finish a job in a certain number of days.4 workers dropped out on second day,4 more workers dropped out on the third day and so on.It took 8 more days to finish the work.Find the number of days in which the work was complete.
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped the second day, four more workers dropped the third day and so on. It takes 8 more days to finish the work now. Find the number of days in which the work was completed.
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four wirkers dropped from the work in the second day. Four workers dropped in third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
[ Let the no. of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]
View SolutionIf they are in G.P.Write next one terms.
a,2a, 3a, 4a,......
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'x' then
150x=x+82[2×150+(x+8−1)(−4)]
View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]
View Solution150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'r' then
150x=x+82[2×150+(x+8−1)(−4)]
View Solution150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on.
View SolutionAbout 150 workers were engaged to finish a piece of work in a certain number of days. Four workers stopped working on the second day, four more workers stopped their work on the third day and so on. It took 8 more days to finish the work. Then the number of days in which the work was completed is 29 days b. 24 days c. 25 days d. none of these
View SolutionIn a factory, 150 workers were engaged to finish a piece of work in a certain number of days. However, if 4 workers are dropped everyday, except the first day, it will take 8 more days to finish the work. Find the number of days in which the work was to be completed.
View Solution