30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:40 days


To solve the problem step by step, we can use the concept of direct proportion. Here’s how we can approach it:

Step 1: Calculate the Total Work
First, we need to determine the total amount of work done by 30 men in 28 days. The total work can be calculated using the formula:

Total Work=Number of Men×Number of Days

So, for 30 men working for 28 days, the total work is:

Total Work=30×28=840 man-days

Step 2: Set Up the Equation for 21 Men
Next, we need to find out how many days (let's call it x) it will take for 21 men to complete the same amount of work (840 man-days). We can set up the equation as follows:

Total Work=Number of Men×Number of Days

For 21 men, the equation becomes:

840=21×x

Step 3: Solve for x
Now, we can solve for x:

x=84021

Calculating this gives:

x=40

Conclusion
Thus, it will take 21 men a total of 40 days to finish the work.

Updated on:18/9/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

    A52
    B31
    C13
    D65
  • 10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?

    A2
    B4
    C5
    D11