30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?
The correct Answer is:40 days
To solve the problem step by step, we can use the concept of direct proportion. Here’s how we can approach it:
Step 1: Calculate the Total Work
First, we need to determine the total amount of work done by 30 men in 28 days. The total work can be calculated using the formula:
Total Work=Number of Men×Number of Days
So, for 30 men working for 28 days, the total work is:
Total Work=30×28=840 man-days
Step 2: Set Up the Equation for 21 Men
Next, we need to find out how many days (let's call it x) it will take for 21 men to complete the same amount of work (840 man-days). We can set up the equation as follows:
Total Work=Number of Men×Number of Days
For 21 men, the equation becomes:
840=21×x
Step 3: Solve for x
Now, we can solve for x:
x=84021
Calculating this gives:
x=40
Conclusion
Thus, it will take 21 men a total of 40 days to finish the work.
First, we need to determine the total amount of work done by 30 men in 28 days. The total work can be calculated using the formula:
Next, we need to find out how many days (let's call it x) it will take for 21 men to complete the same amount of work (840 man-days). We can set up the equation as follows:
Now, we can solve for x:
Thus, it will take 21 men a total of 40 days to finish the work.
Topper's Solved these Questions
- DIRECT AND INVERSE PROPORTIONSBOOK - RS AGGARWALCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - TEST PAPER - 12 (Mark against the correct answer in each of the following )
7 Videos
- DIRECT AND INVERSE PROPORTIONSBOOK - RS AGGARWALCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - TEST PAPER -12 (Fill in the blanks )
5 Videos
- DIRECT AND INVERSE PROPORTIONSBOOK - RS AGGARWALCHAPTER - DIRECT AND INVERSE PROPORTIONSEXERCISE - EXERCISE 12C
10 Videos
- DATA HANDLING BOOK - RS AGGARWALCHAPTER - DATA HANDLING EXERCISE - Exercise 21C
11 Videos
- EXPONENTS BOOK - RS AGGARWALCHAPTER - EXPONENTS EXERCISE - TEST PAPER-2
18 Videos
Similar Questions
Knowledge Check
If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
A52B31C13D6510 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?
A2B4C5D11
40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View SolutionIf 9 men working 712 hours a day can finish a piece of work in 20 days, then how many days will be taken by 12 men, working 6 hours a day to finish the work? It is being given that 2 men of latter type work as much as 3 men of the former type. 11 b. 13 c. 912 d. 1212
View SolutionIf 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 20 days. In how many days will A alone finish the work?
View Solution