4 men and10 women were put on a work. They completed 13 of the work in 4 days. After this 2 men and 2 women were increased. They completed 29 more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased? 8 b. 32 c. 50 d. 55
Step by step video & image solution for 4 men and10 women were put on a work. They completed 1/3 of the work in 4 days. After this 2 men and 2 women were increased. They completed 2/9 more of the work in 2 days. If the remaining work is to be completed in 3 days, then how many more women must be increased? 8 b. 32 c. 50 d. 55 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
Similar Questions
4 men and 10 women can complete 13 is part of work in 4 days. Now, 2 more men and 2 women joined the work and 29 additional work is completed in 2 days. If remaining work is to be completed in 3 days, then how many more women should join the work?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution20 men or 24 women can complete a piece of work in 20 days. If 30 men and 112 women under take to complete the work, the work will be completed in:
View Solution6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined
View Solution2 men and 3 women together or 4 men together can complete a piece of work in 20 days.3 men and 3 women will complete the same work in :
View Solution24 men can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How
many more days will the remaining men now take to
complete the remaining work?View Solution