A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A in 60 days; B in 120 days and C in 40 days


To solve the problem step by step, we will denote the amount of work done by A, B, and C in one day as X, Y, and Z respectively.

Step 1: Set up the equations based on the given information

1. A and B can complete the work in 40 days:
X+Y=140(Equation 1)

2. B and C can complete the work in 30 days:
Y+Z=130(Equation 2)

3. C and A can complete the work in 24 days:
Z+X=124(Equation 3)

Step 2: Rewrite the equations

We can rewrite the equations to express them in terms of work done per day:
- From Equation 1:
X+Y=140

- From Equation 2:
Y+Z=130

- From Equation 3:
Z+X=124

Step 3: Solve the equations

Now we will solve these equations step by step.

Subtract Equation 2 from Equation 1:
(X+Y)(Y+Z)=140130
This simplifies to:
XZ=140130
Finding a common denominator (120):
XZ=34120=1120(Equation 4)

Add Equation 3 and Equation 4:
(Z+X)+(XZ)=1241120
This simplifies to:
2X=51120=4120=130
Thus,
X=160(A's work rate)

Step 4: Substitute X back to find Y and Z

Substituting X into Equation 1:
160+Y=140
Finding a common denominator (120):
2120+Y=3120
Thus,
Y=31202120=1120(B's work rate)

Substituting Y into Equation 2:
1120+Z=130
Finding a common denominator (120):
1120+Z=4120
Thus,
Z=41201120=3120=140(C's work rate)

Step 5: Calculate the time taken by each to finish the work alone

- Time taken by A to finish the work alone:
TimeA=1X=1160=60 days

- Time taken by B to finish the work alone:
TimeB=1Y=11120=120 days

- Time taken by C to finish the work alone:
TimeC=1Z=1140=40 days

Final Answer:
- A can finish the work alone in 60 days.
- B can finish the work alone in 120 days.
- C can finish the work alone in 40 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions