A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?
The correct Answer is:A in 60 days; B in 120 days and C in 40 days
To solve the problem step by step, we will denote the amount of work done by A, B, and C in one day as X, Y, and Z respectively.
Step 1: Set up the equations based on the given information
1. A and B can complete the work in 40 days:
X+Y=140(Equation 1)
2. B and C can complete the work in 30 days:
Y+Z=130(Equation 2)
3. C and A can complete the work in 24 days:
Z+X=124(Equation 3)
Step 2: Rewrite the equations
We can rewrite the equations to express them in terms of work done per day:
- From Equation 1:
X+Y=140
- From Equation 2:
Y+Z=130
- From Equation 3:
Z+X=124
Step 3: Solve the equations
Now we will solve these equations step by step.
Subtract Equation 2 from Equation 1:
(X+Y)−(Y+Z)=140−130
This simplifies to:
X−Z=140−130
Finding a common denominator (120):
X−Z=3−4120=−1120(Equation 4)
Add Equation 3 and Equation 4:
(Z+X)+(X−Z)=124−1120
This simplifies to:
2X=5−1120=4120=130
Thus,
X=160(A's work rate)
Step 4: Substitute X back to find Y and Z
Substituting X into Equation 1:
160+Y=140
Finding a common denominator (120):
2120+Y=3120
Thus,
Y=3120−2120=1120(B's work rate)
Substituting Y into Equation 2:
1120+Z=130
Finding a common denominator (120):
1120+Z=4120
Thus,
Z=4120−1120=3120=140(C's work rate)
Step 5: Calculate the time taken by each to finish the work alone
- Time taken by A to finish the work alone:
TimeA=1X=1160=60 days
- Time taken by B to finish the work alone:
TimeB=1Y=11120=120 days
- Time taken by C to finish the work alone:
TimeC=1Z=1140=40 days
Final Answer:
- A can finish the work alone in 60 days.
- B can finish the work alone in 120 days.
- C can finish the work alone in 40 days.
X+Y=140(Equation 1)
Y+Z=130(Equation 2)
Z+X=124(Equation 3)
- From Equation 1:
X+Y=140
Y+Z=130
Z+X=124
(X+Y)−(Y+Z)=140−130
This simplifies to:
X−Z=140−130
Finding a common denominator (120):
X−Z=3−4120=−1120(Equation 4)
(Z+X)+(X−Z)=124−1120
This simplifies to:
2X=5−1120=4120=130
Thus,
X=160(A's work rate)
160+Y=140
Finding a common denominator (120):
2120+Y=3120
Thus,
Y=3120−2120=1120(B's work rate)
1120+Z=130
Finding a common denominator (120):
1120+Z=4120
Thus,
Z=4120−1120=3120=140(C's work rate)
TimeA=1X=1160=60 days
TimeB=1Y=11120=120 days
TimeC=1Z=1140=40 days
- A can finish the work alone in 60 days.
- B can finish the work alone in 120 days.
- C can finish the work alone in 40 days.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
How long will it take them to do the work, working together ?
View SolutionA and B can do a piece of work in 18 days .B and C in 24 days and A and C in 36 days .In what time can they do it , all works together
View SolutionA and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together ?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job ?
View SolutionA and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View SolutionA and B can finish a piece of work in 12 days, B and C in 15 days shile C and A in 20 days. How long will they take to finish it together ? How long will each take to finish the work alone ?
View SolutionA can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
View SolutionA, B and C can do a piece of work in 6 days, 12 days and 24 days respectively. In what time will they altogether do it ?
View SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View SolutionA can do a piece of work in 24 days, A and B can do it in 16 days and A,B and C in 1023 days. In how many days can A and C do it working together ?
View Solution