A and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A alone,

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:36 days


To find out how many days A alone will take to complete the work, we can follow these steps:

Step 1: Understand the problem
We know the following:
- A and B together can complete the work in 24 days.
- B and C together can complete the work in 36 days.
- A, B, and C together can complete the work in 18 days.

Step 2: Calculate the efficiencies
We can express the efficiencies of the groups as follows:
- Efficiency of A + B = 1/24 (work done in one day)
- Efficiency of B + C = 1/36
- Efficiency of A + B + C = 1/18

Step 3: Find the efficiency of A
To find the efficiency of A, we can use the formula:
Efficiency of A=Efficiency of (A + B + C)Efficiency of (B + C)

Substituting the values:
Efficiency of A=118136

Step 4: Calculate the LCM
To subtract the fractions, we need a common denominator. The least common multiple (LCM) of 18 and 36 is 36.

Step 5: Rewrite the fractions
Now, we can rewrite the fractions:
118=236
So,
Efficiency of A=236136=136

Step 6: Find the time taken by A alone
The time taken by A to complete the work alone is the reciprocal of the efficiency:
Time taken by A=1Efficiency of A=1136=36 days

Final Answer
A alone will take 36 days to complete the work.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions