A and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A alone,
The correct Answer is:36 days
To find out how many days A alone will take to complete the work, we can follow these steps:
Step 1: Understand the problem
We know the following:
- A and B together can complete the work in 24 days.
- B and C together can complete the work in 36 days.
- A, B, and C together can complete the work in 18 days.
Step 2: Calculate the efficiencies
We can express the efficiencies of the groups as follows:
- Efficiency of A + B = 1/24 (work done in one day)
- Efficiency of B + C = 1/36
- Efficiency of A + B + C = 1/18
Step 3: Find the efficiency of A
To find the efficiency of A, we can use the formula:
Efficiency of A=Efficiency of (A + B + C)−Efficiency of (B + C)
Substituting the values:
Efficiency of A=118−136
Step 4: Calculate the LCM
To subtract the fractions, we need a common denominator. The least common multiple (LCM) of 18 and 36 is 36.
Step 5: Rewrite the fractions
Now, we can rewrite the fractions:
118=236
So,
Efficiency of A=236−136=136
Step 6: Find the time taken by A alone
The time taken by A to complete the work alone is the reciprocal of the efficiency:
Time taken by A=1Efficiency of A=1136=36 days
Final Answer
A alone will take 36 days to complete the work.
---
We know the following:
- A and B together can complete the work in 24 days.
- B and C together can complete the work in 36 days.
- A, B, and C together can complete the work in 18 days.
We can express the efficiencies of the groups as follows:
- Efficiency of A + B = 1/24 (work done in one day)
- Efficiency of B + C = 1/36
- Efficiency of A + B + C = 1/18
To find the efficiency of A, we can use the formula:
Efficiency of A=Efficiency of (A + B + C)−Efficiency of (B + C)
Efficiency of A=118−136
To subtract the fractions, we need a common denominator. The least common multiple (LCM) of 18 and 36 is 36.
Now, we can rewrite the fractions:
118=236
So,
Efficiency of A=236−136=136
The time taken by A to complete the work alone is the reciprocal of the efficiency:
Time taken by A=1Efficiency of A=1136=36 days
A alone will take 36 days to complete the work.
Topper's Solved these Questions
Similar Questions
A and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
C alone,
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A and C together, complete the work ?
View Solution36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?
View SolutionA can do a piece of work in 24 days, A and B can do it in 16 days and A,B and C in 1023 days. In how many days can A and C do it working together ?
View SolutionA and Q together can do a piece of work in 10 days, Q and R can do the same work together in 12 days, while A and R can do together in 15 days. How long each will take to do it separately?
View SolutionA can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?
View SolutionA and B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View SolutionA and B can finish a work in 20 days . A alone can do 15th of the work in 12 days.In how many days can B alone do it?
View SolutionA can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View Solution