A can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:101017 days


To find out how long C would take to complete the work alone, we can follow these steps:

Step 1: Determine the work done by A, B, and C in one day
- A can complete the work in 10 days, so A's work in one day is:
Work done by A in 1 day=110
- B can complete the work in 18 days, so B's work in one day is:
Work done by B in 1 day=118
- A, B, and C together can complete the work in 4 days, so their combined work in one day is:
Work done by A, B, and C in 1 day=14

Step 2: Set up the equation for C's work
- To find the work done by C alone in one day, we can use the formula:
Work done by C in 1 day=Work done by A, B, and CWork done by AWork done by B
- Substituting the values we found:
Work done by C in 1 day=14110118

Step 3: Find a common denominator
- The least common multiple (LCM) of 4, 10, and 18 is 180. Now we convert each fraction:
14=45180,110=18180,118=10180

Step 4: Perform the subtraction
- Now substitute these values into the equation:
Work done by C in 1 day=451801818010180
- Combine the fractions:
Work done by C in 1 day=451810180=17180

Step 5: Calculate the time taken by C to complete the work alone
- The time taken by C to complete the work alone is the inverse of the work done by C in one day:
Time taken by C=1Work done by C in 1 day=18017
- Converting this to a mixed fraction:
18017=101017 days

Final Answer
C would take 101017 days to complete the work alone.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions