A can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
The correct Answer is:101017 days
To find out how long C would take to complete the work alone, we can follow these steps:
Step 1: Determine the work done by A, B, and C in one day
- A can complete the work in 10 days, so A's work in one day is:
Work done by A in 1 day=110
- B can complete the work in 18 days, so B's work in one day is:
Work done by B in 1 day=118
- A, B, and C together can complete the work in 4 days, so their combined work in one day is:
Work done by A, B, and C in 1 day=14
Step 2: Set up the equation for C's work
- To find the work done by C alone in one day, we can use the formula:
Work done by C in 1 day=Work done by A, B, and C−Work done by A−Work done by B
- Substituting the values we found:
Work done by C in 1 day=14−110−118
Step 3: Find a common denominator
- The least common multiple (LCM) of 4, 10, and 18 is 180. Now we convert each fraction:
14=45180,110=18180,118=10180
Step 4: Perform the subtraction
- Now substitute these values into the equation:
Work done by C in 1 day=45180−18180−10180
- Combine the fractions:
Work done by C in 1 day=45−18−10180=17180
Step 5: Calculate the time taken by C to complete the work alone
- The time taken by C to complete the work alone is the inverse of the work done by C in one day:
Time taken by C=1Work done by C in 1 day=18017
- Converting this to a mixed fraction:
18017=101017 days
Final Answer
C would take 101017 days to complete the work alone.
---
- A can complete the work in 10 days, so A's work in one day is:
Work done by A in 1 day=110
- B can complete the work in 18 days, so B's work in one day is:
Work done by B in 1 day=118
- A, B, and C together can complete the work in 4 days, so their combined work in one day is:
Work done by A, B, and C in 1 day=14
- To find the work done by C alone in one day, we can use the formula:
Work done by C in 1 day=Work done by A, B, and C−Work done by A−Work done by B
- Substituting the values we found:
Work done by C in 1 day=14−110−118
- The least common multiple (LCM) of 4, 10, and 18 is 180. Now we convert each fraction:
14=45180,110=18180,118=10180
- Now substitute these values into the equation:
Work done by C in 1 day=45180−18180−10180
- Combine the fractions:
Work done by C in 1 day=45−18−10180=17180
- The time taken by C to complete the work alone is the inverse of the work done by C in one day:
Time taken by C=1Work done by C in 1 day=18017
- Converting this to a mixed fraction:
18017=101017 days
C would take 101017 days to complete the work alone.
Topper's Solved these Questions
Similar Questions
A and B can do a piece of work in 18 days .B and C in 24 days and A and C in 36 days .In what time can they do it , all works together
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?
View SolutionA and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together ?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
How long will it take them to do the work, working together ?
View SolutionA can do a piece of work in 24 days, A and B can do it in 16 days and A,B and C in 1023 days. In how many days can A and C do it working together ?
View SolutionA, B and C can do a piece of work in 6 days, 12 days and 24 days respectively. In what time will they altogether do it ?
View SolutionA can do a piece of work in 10 days, B in 12 days and C in 15 days. All begin together but A leaves the work after 2 days and B leaves 3 days befor the work is finished. How long did the work last ?
View SolutionA can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?
View SolutionA and Q together can do a piece of work in 10 days, Q and R can do the same work together in 12 days, while A and R can do together in 15 days. How long each will take to do it separately?
View Solution