A can do a piece of work in 80 days and B in 100 days. They work together for first 20 days before B goes away. In how many days will A manage to finish the remaining work?
The correct Answer is:44 days
To solve the problem step by step, we will first determine the work done by A and B, then calculate the remaining work after they work together for 20 days, and finally find out how long it will take A to finish the remaining work alone.
Step 1: Determine the work done by A and B
A can complete the work in 80 days, and B can complete it in 100 days.
The efficiency (work done per day) of A is:
Efficiency of A=180 (work units per day)
The efficiency of B is:
Efficiency of B=1100 (work units per day)
Step 2: Find the combined efficiency of A and B
To find the combined efficiency of A and B when they work together, we add their efficiencies:
Combined Efficiency=180+1100
To add these fractions, we need a common denominator. The least common multiple of 80 and 100 is 400. Therefore:
180=5400and1100=4400
Combined Efficiency=5400+4400=9400
Step 3: Calculate the work done in the first 20 days
Now, we calculate the total work done by A and B together in the first 20 days:
Work done in 20 days=Combined Efficiency×Time=9400×20
Work done in 20 days=180400=920 of the total work
Step 4: Determine the total work
Since A can complete the total work in 80 days, the total work can be represented in terms of work units:
Total Work=80×Efficiency of A=80×180=1 (total work units)
Step 5: Calculate the remaining work
The remaining work after A and B have worked together for 20 days is:
Remaining Work=1−920=2020−920=1120
Step 6: Calculate how long it will take A to finish the remaining work
Now, we need to find out how long it will take A to finish the remaining 1120 of the work alone. A's efficiency is 180, so we can set up the equation:
Time=Remaining WorkEfficiency of A=1120180=1120×80=44 days
Final Answer
A will take 44 days to finish the remaining work alone.
---
Efficiency of A=180 (work units per day)
Efficiency of B=1100 (work units per day)
Combined Efficiency=180+1100
180=5400and1100=4400
Combined Efficiency=5400+4400=9400
Work done in 20 days=Combined Efficiency×Time=9400×20
Work done in 20 days=180400=920 of the total work
Total Work=80×Efficiency of A=80×180=1 (total work units)
Remaining Work=1−920=2020−920=1120
Time=Remaining WorkEfficiency of A=1120180=1120×80=44 days
Topper's Solved these Questions
- DIRECT AND INVERSE VARIATIONSBOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (A)
13 Videos
- DIRECT AND INVERSE VARIATIONSBOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (B)
11 Videos
- DATA HANDLING BOOK - ICSECHAPTER - DATA HANDLING EXERCISE - EXERCISE 22 (B)
10 Videos
- EXPONENTS (POWERS) BOOK - ICSECHAPTER - EXPONENTS (POWERS) EXERCISE - EXERCISE 2(B)
50 Videos
Similar Questions
A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work ?
View SolutionA can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?
View SolutionA can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?
View SolutionA and B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?
View SolutionA can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?
View SolutionA can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together ?
View SolutionA and B together can do a piece of work in 15 days. If one day's work of A be 112 times one day's work of B, find how many days will each take to finish the work alone?
View SolutionA can do a work in 15 days and B in 20 days. If they work together on it for 4 days, what fraction of the work will be left ?
View SolutionA and B can do a piece of work in 45 days and 40 days respectively.They began the work together but A leaves after some days and B finishes the remaining work in 23 days. After how many days did A leave the work ?
View SolutionA can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
View Solution