A contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
Step by step video & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Similar Questions
If the work of a building is completed late after a certain amount of time, that is. The form was fined. It is as follows: Rs.200 for first day, Rs.250 for second day, Rs.300 for 3rd day. Every day. The penalty is' Rs.50 a pound higher than the previous day's fine. If a contractor takes more than 30 days to complete a job, calculate the penalty he must pay?
04:16View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
02:47View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
03:23View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : Rs 200 for the first day . Rs 250 for the second day , Rs 300 for the third day , etc. the penalty for each succeeding day being Rs50 more than for the preceding day. How much money the contractor has to pay as penalty , if the has delayed the work by 30 days?
02:00View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?
06:01View Solutionਨਿਰਮਾਣ ਕਾਰਜ ਨਾਲ ਸਬੰਧਤ ਕਿਸੇ ਠੇਕੇ ਵਿੱਚ ਕਿਸੇ ਨਿਸ਼ਚਿਤ ਮਿਤੀ ਤੋਂ ਬਾਅਦ ਕੰਮ ਦੇਰੀ ਨਾਲ ਪੂਰਾ ਕਰਨ ਲਈ, ਜੂਰਮਾਨਾ ਲਗਾਉਣ ਦੀ ਵਿਵਸਥਾ ਇਸ ਪ੍ਰਕਾਰ ਹੈ ਪਹਿਲੇ ਦਿਨ ਦੇ ਲਈ Rs 200 ਦੂਸਰੇ ਦਿਨ ਲਈ Rs 250 ਤੀਸਰੇ ਦਿਨ ਲਈ Rs 300 ਆਦਿ ਭਾਵ ਹਰੇਕ ਅਗਲੇ ਦਿਨ ਦਾ ਜੁਰਮਾਨਾ ਆਪਣੇ ਤੋਂ ਠੀਕ ਪਹਿਲੇ ਦਿਨ ਦੇ ਜੁਰਮਾਨੇ ਨਾਲੋਂ Rs 50 ਵੱਧ ਹੈ। ਇੱਕ ਠੇਕੇਦਾਰ ਨੂੰ ਜੁਰਮਾਨੇ ਦੇ ਰੂਪ ਵਿੱਚ ਕਿੰਨੀ ਰਕਮ ਦੇਣੀ ਪਵੇਗੀ, ਜੇਕਰ ਉਹ ਇਸ ਕੰਮ ਵਿੱਚ 30 ਦਿਨ ਦੀ ਦੇਰੀ ਕਰ ਦਿੰਦਾ ਹੈ?
04:19View SolutionA contract of construction job specifies a penalty for delay of completion beyond a certain date as follows:₹200 for the first day,₹250 for the second day,₹300 for the thrid day etc.the penalty for each succeeding day being ₹50 more than for the preceding day.How much does a delay of 30 days cost the contractor?
03:52View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date is as follows,
₹200 for 1st day,₹250 for 2nd day,₹300 for 3rd day and so on.If the contractor pays 27,750 as penalty,find the number of days for which the work is delayed.06:04View Solution