A contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?
The correct Answer is:(i) Rs 4800 (ii) 20 days
Step by step video, text & image solution for A contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty? by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.
Updated on:21/07/2023Topper's Solved these Questions
- ARITHMETIC PROGRESSIONS BOOK - VK GLOBAL PUBLICATIONCHAPTER - ARITHMETIC PROGRESSIONS EXERCISE - SELF ASSESSMENT TEST
10 Videos
- ARITHMETIC PROGRESSIONS BOOK - VK GLOBAL PUBLICATIONCHAPTER - ARITHMETIC PROGRESSIONS EXERCISE - PROFICIENCY EXERCISE ( SHORT ANSWER QUESTION II)
39 Videos
- AREAS RELATED TO CIRCLESBOOK - VK GLOBAL PUBLICATIONCHAPTER - AREAS RELATED TO CIRCLESEXERCISE - Self -Assessment Test
11 Videos
- CIRCLES BOOK - VK GLOBAL PUBLICATIONCHAPTER - CIRCLES EXERCISE - SELF - ASSESSMENT TEST
11 Videos
Similar Questions
A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?
View SolutionA contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?
View Solution
Knowledge Check
If you save Rs. 1 today, Rs. 2 the next day, Rs. 3 the succeeding day and so on, what will be your total savings in 365 days?
A66579B66795C56795Dnone of these
A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day, Rs. 250 for second day, Rs. 300 for thirdday and so on. If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.
View SolutionIf man A complete a work in 10 days & man B complete the same work in 15 days , in how many days the work is completed if they work together ?
View SolutionCertain sum is sufficient to pay wage to A for 15 days or to B for 30 days. For how many days is the sum sufficient to pay both A and B?
View Solution18 men can earn Rs. 360 in 5 days . How much money will 15 men earn in 9 days ?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionLalit earns Rs. x per day and spends Rs. y per day. How much does he save in 30 days?
View SolutionSmith asked daddy to give Rs100 on first day and go on decreasing by Rs10 daily. How much money has he collected in 10 days?
View Solution