A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A100
    B60
    C75
    DNone of these
  • A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only one-third of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

    A70
    B75
    C80
    D85
  • 25 persons complete a work in 50 days. In how many days will 10 persons complete the work ?

    A120
    B125
    C100
    D215