A is thrice as efficient as B and hence completes a work in 40
days less than the number days taken by B. What will be
the number of days taken by both of them when working
together ?
22.5 days
15 days
20 days
18 days
The correct Answer is:(b)
Let efficiency of B is x
Days are inversaly proportional to efficiency.
According to question
3x−x=40
2x=40
x=20
Time taken by A=xdays=20days
Time taken by B=3x days =3×20=60 days
Time taken by A and B togeter =20×6080=15 days
Related Playlists
Similar Questions
A is thrice as efficient as B and hence completes a work in 40 days less than the number of days taken by B. What will be the number of days taken by both of them when working together?
View SolutionA is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?
View SolutionIf X works 3 tims as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they cn complete the work working together.
View SolutionA is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.
View SolutionX works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View SolutionX works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.
View SolutionIf A is twice as efficient as B, and A and B together can complete a work in 20 days, then find the number of days in which B can do the work alone.
(a)60 days
(b) 50 days
(c)30 days
(d)40 daysView SolutionA is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?
View SolutionA is three times more efficient worker than B and is therefore able to complete a work in 60 days less than B. What is the number of days that a and B together will take to complete the work ?
View SolutionIf a work can be completed by A in 30 days and by B in 60 days. Then, the number of days taken by them to complete the work, working together is
View Solution