A particular work can be completed by 6 men and 6 women in 24 days, whereas the same work can be completed by 8 men and 12 women in 15 days. Find :
The time taken by 4 men and 6 women to complete the same work.
The correct Answer is: days
To solve the problem step by step, we will first analyze the information given and set up equations based on the efficiencies of men and women.
Step 1: Establish the work done by men and women
We know from the problem that:
- 6 men and 6 women can complete the work in 24 days.
- 8 men and 12 women can complete the same work in 15 days.
Let’s denote the work done by one man in one day as M and the work done by one woman in one day as W.
Step 2: Set up the equations
From the first scenario:
- The total work done by 6 men and 6 women in 24 days can be expressed as:
(6M+6W)×24=Total Work(1)
From the second scenario:
- The total work done by 8 men and 12 women in 15 days can be expressed as:
(8M+12W)×15=Total Work(2)
Since both expressions equal the total work, we can set them equal to each other:
(6M+6W)×24=(8M+12W)×15
Step 3: Simplify the equation
Expanding both sides:
144M+144W=120M+180W
Now, rearranging the equation:
144M−120M=180W−144W
24M=36W
Step 4: Find the relationship between men and women
Dividing both sides by 12:
2M=3W
This gives us the relationship:
M=32W(3)
Step 5: Set up the equation for 4 men and 6 women
Now, we need to find the time taken by 4 men and 6 women to complete the same work. Let x be the number of days taken by 4 men and 6 women. The work done can be expressed as:
(4M+6W)×x=Total Work
Step 6: Substitute M in terms of W
Using equation (3):
4M+6W=4(32W)+6W=6W+6W=12W
Thus, the equation becomes:
12W×x=Total Work(4)
Step 7: Use the total work from either scenario
Now, we can use the total work from either scenario. Let's use the first scenario:
Total Work=(6M+6W)×24=(6×32W+6W)×24=(9W+6W)×24=15W×24=360W
Step 8: Set the equations equal
Now we can set equation (4) equal to the total work:
12W×x=360W
Step 9: Solve for x
Dividing both sides by 12W:
x=360W12W=30
Final Answer
The time taken by 4 men and 6 women to complete the same work is 30 days.
---
- 6 men and 6 women can complete the work in 24 days.
- 8 men and 12 women can complete the same work in 15 days.
- The total work done by 6 men and 6 women in 24 days can be expressed as:
(6M+6W)×24=Total Work(1)
- The total work done by 8 men and 12 women in 15 days can be expressed as:
(8M+12W)×15=Total Work(2)
(6M+6W)×24=(8M+12W)×15
144M+144W=120M+180W
144M−120M=180W−144W
24M=36W
2M=3W
This gives us the relationship:
M=32W(3)
(4M+6W)×x=Total Work
4M+6W=4(32W)+6W=6W+6W=12W
12W×x=Total Work(4)
Total Work=(6M+6W)×24=(6×32W+6W)×24=(9W+6W)×24=15W×24=360W
12W×x=360W
x=360W12W=30
Topper's Solved these Questions
- DIRECT AND INVERSE VARIATIONSBOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (D)
13 Videos
- DIRECT AND INVERSE VARIATIONSBOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (E)
19 Videos
- DIRECT AND INVERSE VARIATIONSBOOK - ICSECHAPTER - DIRECT AND INVERSE VARIATIONSEXERCISE - EXERCISE 10 (B)
11 Videos
- DATA HANDLING BOOK - ICSECHAPTER - DATA HANDLING EXERCISE - EXERCISE 22 (B)
10 Videos
- EXPONENTS (POWERS) BOOK - ICSECHAPTER - EXPONENTS (POWERS) EXERCISE - EXERCISE 2(B)
50 Videos
Similar Questions
A particular work can be completed by 6 men and 6 women in 24 days, whereas the same work can be completed by 8 men and 12 women in 15 days. Find :
According to the amount of work done, one man is equivalent to how many women.
View Solution3 men and 4 boys can complete a certain amount of work in 28 days, whereas 4 men and 6 boys can complete the same work in 20 days. Find :
The number of days required by 7 men and 6 boys to complete the same work.
View SolutionIf 12 men or 18 women can complete a piece of work in 7 days, in how many days can 4 men and 8 women complete the same work ?
View Solution2 men or 3 women can do a piece of work in 45 days. Find, in how many days will 6 men and 1 woman be able to complete the same work ?
View Solution8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A and C together, complete the work ?
View Solution8 men or 6 women earn Rs. 960 in one day.
One day's earning of 4 men and 5 women.
View SolutionIf 78 men can do a work in 140 days, in how many days will 42 men do the same work ?
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
C alone,
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A alone,
View Solution