A particular work can be completed by 6 men and 6 women in 24 days, whereas the same work can be completed by 8 men and 12 women in 15 days. Find :
The time taken by 4 men and 6 women to complete the same work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is: = 30 days


To solve the problem step by step, we will first analyze the information given and set up equations based on the efficiencies of men and women.

Step 1: Establish the work done by men and women

We know from the problem that:
- 6 men and 6 women can complete the work in 24 days.
- 8 men and 12 women can complete the same work in 15 days.

Let’s denote the work done by one man in one day as M and the work done by one woman in one day as W.

Step 2: Set up the equations

From the first scenario:
- The total work done by 6 men and 6 women in 24 days can be expressed as:
(6M+6W)×24=Total Work(1)

From the second scenario:
- The total work done by 8 men and 12 women in 15 days can be expressed as:
(8M+12W)×15=Total Work(2)

Since both expressions equal the total work, we can set them equal to each other:
(6M+6W)×24=(8M+12W)×15

Step 3: Simplify the equation

Expanding both sides:
144M+144W=120M+180W

Now, rearranging the equation:
144M120M=180W144W
24M=36W

Step 4: Find the relationship between men and women

Dividing both sides by 12:
2M=3W
This gives us the relationship:
M=32W(3)

Step 5: Set up the equation for 4 men and 6 women

Now, we need to find the time taken by 4 men and 6 women to complete the same work. Let x be the number of days taken by 4 men and 6 women. The work done can be expressed as:
(4M+6W)×x=Total Work

Step 6: Substitute M in terms of W

Using equation (3):
4M+6W=4(32W)+6W=6W+6W=12W

Thus, the equation becomes:
12W×x=Total Work(4)

Step 7: Use the total work from either scenario

Now, we can use the total work from either scenario. Let's use the first scenario:
Total Work=(6M+6W)×24=(6×32W+6W)×24=(9W+6W)×24=15W×24=360W

Step 8: Set the equations equal

Now we can set equation (4) equal to the total work:
12W×x=360W

Step 9: Solve for x

Dividing both sides by 12W:
x=360W12W=30

Final Answer

The time taken by 4 men and 6 women to complete the same work is 30 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions