Doubtnut Promotions Sticky

A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? a. 2.5 days, 7.5 days b. 5 days, 8.5 days c. 5 days, 15 days d. none of these

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for A started a work and left after working for 2 days. Then B was called and he finished the work in 9 days. Had A left the work after working for 3 days, B would have finished the remaining work in 6 days. In how many days can each of them, working , alone, finish the whole work? a. 2.5\ days ,\ 7. 5\ d a y s b. 5\ d a y s ,\ 8. 5\ d a y s c. 5\ d a y s ,\ 15\ d a y s d. none of these by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Questions