A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.
To solve the problem, we will follow these steps:
Step 1: Define the variables
Let the time taken by B to finish the work be x days. According to the problem, A takes 6 days less than B, so the time taken by A is x−6 days.
Step 2: Write the work done in one day
The total work can be represented as W. The work done by A in one day is:
Work done by A in one day=Wx−6
The work done by B in one day is:
Work done by B in one day=Wx
Step 3: Set up the equation for combined work
According to the problem, A and B together can finish the work in 4 days. Therefore, the work done by A and B together in one day is:
Work done by A and B in one day=W4
Thus, we can set up the equation:
Wx−6+Wx=W4
Step 4: Simplify the equation
We can cancel W from all terms (assuming W≠0):
1x−6+1x=14
Step 5: Find a common denominator
The common denominator for the left-hand side is x(x−6):
x+(x−6)x(x−6)=14
This simplifies to:
2x−6x(x−6)=14
Step 6: Cross-multiply to eliminate the fraction
Cross-multiplying gives:
4(2x−6)=x(x−6)
Expanding both sides:
8x−24=x2−6x
Step 7: Rearrange the equation
Rearranging all terms to one side results in:
x2−6x−8x+24=0
This simplifies to:
x2−14x+24=0
Step 8: Factor the quadratic equation
Now we will factor the quadratic equation:
x2−14x+24=(x−12)(x−2)=0
Step 9: Solve for x
Setting each factor to zero gives:
x−12=0orx−2=0
Thus, we have:
x=12orx=2
Step 10: Determine the valid solution
Since x represents the time taken by B, we check both solutions:
- If x=2, then A would take 2−6=−4 days, which is not possible.
- If x=12, then A would take 12−6=6 days, which is valid.
Conclusion
Therefore, the time taken by B to finish the work is:
12 days
Let the time taken by B to finish the work be x days. According to the problem, A takes 6 days less than B, so the time taken by A is x−6 days.
The total work can be represented as W. The work done by A in one day is:
Work done by A in one day=Wx−6
The work done by B in one day is:
Work done by B in one day=Wx
According to the problem, A and B together can finish the work in 4 days. Therefore, the work done by A and B together in one day is:
Work done by A and B in one day=W4
Thus, we can set up the equation:
Wx−6+Wx=W4
We can cancel W from all terms (assuming W≠0):
1x−6+1x=14
The common denominator for the left-hand side is x(x−6):
x+(x−6)x(x−6)=14
This simplifies to:
2x−6x(x−6)=14
Cross-multiplying gives:
4(2x−6)=x(x−6)
Expanding both sides:
8x−24=x2−6x
Rearranging all terms to one side results in:
x2−6x−8x+24=0
This simplifies to:
x2−14x+24=0
Now we will factor the quadratic equation:
x2−14x+24=(x−12)(x−2)=0
Setting each factor to zero gives:
x−12=0orx−2=0
Thus, we have:
x=12orx=2
Since x represents the time taken by B, we check both solutions:
- If x=2, then A would take 2−6=−4 days, which is not possible.
- If x=12, then A would take 12−6=6 days, which is valid.
Therefore, the time taken by B to finish the work is:
12 days
Topper's Solved these Questions
Similar Questions
A takes 10 days less than the time taken by B to finish a piece of work. If both A and B together can finish the work in 12 days, find the time taken by B to finish the work.
View Solution2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.
View Solution2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the work, and also that taken by 1 man alone.
View SolutionFormulate the following problems as a pair of equations, and hence find their solutions:
(i) Ritu can row downstream 20 km in 2 hours, and upstream 4 km in 2 hours. Find her speed of rowing in still water and the speed of the current.
(ii) 2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men can finish it in 3 days. Find the time taken by 1 woman alone to finish the work, and also that taken by 1 man alone.
(iii) Roohi travels 300 km to her home partly by train and partly by bus. She takes 4 hours if she travels 60 km by train and the remaining by bus. If she travels 100 km by train and the remaining by bus, she takes 10 minutes longer. Find the speed of the train and the bus separately.
View SolutionB takes 16 days less than A to do a certain piece of work. If both working together can complete the work in 15 days, in how many days will B alone complete the work ?
View Solution8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.
View Solution3 men and 4 boys can do a piece of work in 14 days, while 4 men and 6 boys can do it in 10 days. How long would it take 1 boy to finish the work?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View SolutionA can do a piece of work in 20 days and B in 15 days. They worked together on it for 6 days and then A left. How long will B take to finish the remaining work ?
View Solution6 men and 8 boys can do a piece of work in 7 days, while 8 men and 12 boys do the same work in 5 days. How long would it take one boy to finish the same work?
View Solution