A takes 6 days less than the time taken by B to finish a piece of work. If both A and B together can finish it in 4 days . Find the time taken by B to finish the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we will follow these steps:

Step 1: Define the variables
Let the time taken by B to finish the work be x days. According to the problem, A takes 6 days less than B, so the time taken by A is x6 days.

Step 2: Write the work done in one day
The total work can be represented as W. The work done by A in one day is:
Work done by A in one day=Wx6
The work done by B in one day is:
Work done by B in one day=Wx

Step 3: Set up the equation for combined work
According to the problem, A and B together can finish the work in 4 days. Therefore, the work done by A and B together in one day is:
Work done by A and B in one day=W4
Thus, we can set up the equation:
Wx6+Wx=W4

Step 4: Simplify the equation
We can cancel W from all terms (assuming W0):
1x6+1x=14

Step 5: Find a common denominator
The common denominator for the left-hand side is x(x6):
x+(x6)x(x6)=14
This simplifies to:
2x6x(x6)=14

Step 6: Cross-multiply to eliminate the fraction
Cross-multiplying gives:
4(2x6)=x(x6)
Expanding both sides:
8x24=x26x

Step 7: Rearrange the equation
Rearranging all terms to one side results in:
x26x8x+24=0
This simplifies to:
x214x+24=0

Step 8: Factor the quadratic equation
Now we will factor the quadratic equation:
x214x+24=(x12)(x2)=0

Step 9: Solve for x
Setting each factor to zero gives:
x12=0orx2=0
Thus, we have:
x=12orx=2

Step 10: Determine the valid solution
Since x represents the time taken by B, we check both solutions:
- If x=2, then A would take 26=4 days, which is not possible.
- If x=12, then A would take 126=6 days, which is valid.

Conclusion
Therefore, the time taken by B to finish the work is:
12 days

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions