A takes 6 hours less than B to complete a work. If together they complete the work in 13 hours 20 minutes, find how much time will B alone take to complete the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Let, B alone completes the work in x hours, then A alone will complete the work in (x-6) hours.
1x6+1x=340 (13hr+20min=403hrs.)
x+x6(x6)x=340
3x218x=80x240
3x298x+240=0
3x290x8x+240=0
3x(x30)8(x30)=0
(x30)(3x8)=0
x=30orx=83
x=30 (ifx=83,then x-6 in negative) B alone will take 30 hours to complete the work.

Updated on:21/07/2023
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A project manager estimates that a project will take x hours to complete, where x gt 100. The goal is for the estimate to be within 10 hours of the time it will actually take to complete the project. If the manager meets the goal and it takes y hours to complete the project, which of the following inequalities represents the relationship between the estimated time and the actual completion time?

    Ax+y<10
    By>x+10
    Cy<x10
    D10<yx<10
  • A plumber works twice as fast as his apprentice. After the plumber has worked alone for 3 hours, his apprentice joins him and working together they complete the job 4 hours later. How many hours would it have taken the plumber to do the entire job by himself?

    A9
    B12
    C14
    D18