A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8 days b. 12 days c. 9 days d. 10 days
Step by step video & image solution for A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8\ d a y s b. 12\ d a y s c. 9\ d a y s d. 10\ d a y s by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Related Playlists
Similar Questions
A job can be done by 3 skilled worksmen in 20 days or by 5 boys in 30 days. How many days will they take if they work together? 8 days b. 10 days c. 12 days d. 11 days
View Solution5 men can complete a job in 8 days. How many days will it take if 12 men do the job?
View Solution12 men complete a work in 9 days. After they have worked for 6 days, 6 more men join them. How many days will they take to complete the remaining work? 2 days b. 3 days c. 4 days d. 5days e. none of these
View SolutionA and B together can do a piece of work in 12 days and A alone can complete the work in 18 days. How long will B alone take to complete the job ?
View SolutionA can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionX can do a piece of work in 40 days. He works at it for 8 days and then Y finished it in 16 days. How long will they together take to complete the work ? 1313 days b. 15 days c. 20 days d. 56 days
View SolutionShantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?
View SolutionA and B can do a piece of work in 30 days, while B and C can do the same work in 24 days and C and A in 20 days. They all work together for 10 days when B and C leave. How many days more will A take to finish the work ? 18 days b. 24 days c. 30 days d. 36 days
View Solution8 men can complete a piece of work in 20 days. 8 women can complete the same work in 32 days. In how many days will 5 men and 8 women together complete the same work? 10days b. 12 days c. 14 days d. 16 days e. none of these
View SolutionIf 20 men take 30 days to complete a job, in how many days can 25 men complete the job?
View Solution