Doubtnut Promotions Sticky

Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is 12 days b.  14 days c. 36 days d. 40 days

Video Solution
Doubtnut Promotions Banner
|
Answer

Step by step video & image solution for Madhu takes twice as much time as Uma to complete a work and Rahul does it in the same time as Madhu and Uma together. If all three working together can finish the work in 6 days, then the time taken by Madhu to finish the work is 12\ d a y s b. \ 14\ d a y s c. 36\ d a y s d. 40\ d a y s by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Related Playlists


Similar Questions