Twelve persons can do a piece of work in 20 days. How many persons are required to do the same in 24 days?
20
10
15
18
The correct Answer is:B
When amount of work is constant, number of persons vary inversely with number of days required to complete the work.
Let x number of persons can do the work in 24 days.
∴x×24=20×12⇒x=10
Hence, the correct option is (b).
Related Playlists
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - CONCEPT APPLICATION (LEVEL 3)30videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - ASSESSMENT TESTS (TEST 1)12videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - RATIO AND ITS APPLICATIONSEXERCISE - CONCEPT APPLICATION (LEVEL 1)33videos
RATIO AND ITS APPLICATIONS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - NUMBER SYSTEMEXERCISE - ASSESSMENT TESTS24videos
NUMBER SYSTEM
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - Set theoryEXERCISE - ASSESSMENT TEST Test 212videos
Set theory
Similar Questions
30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?
View Solution35 women can do a piece of work in 15 days. How many women would be required to do the same work in 25 days?
View Solution12 persons can do a piece of work in 4 days. How many persons are required to complete 8 times the work in half the time?
View Solution15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?
View Solution36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
View Solution36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
प्रतिदिन 8 घंटे कार्य करके 36 लोग किसी कार्य की 3 इकाई 12 दिनों में कर सकते हैं| यदि वे एक दिन में 6 घंटे कार्य करें तो 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?View SolutionIf 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
View SolutionIf 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is
View Solution24 men can do a piece of work in 17 days. How many men will be able to do it in 51 days?
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View Solution