Doubtnut Promotions Sticky

If 4 men or 6 women can do a piece of work in 24 days, then how many men should join 3 women to complete the work in 16 days

A

6

B

5

C

4

D

2

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:C


Obtain the relation between Men and Women capacity and use 'Mandays' concept.

|
Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    If 12 men or 20 women can do a work in 54 days, then in how many days can 9 men and 12 women together do the work?

    A38
    B32
    C40
    D35
  • Question 1 - Select One

    If 12 men or 18 women can do a piece of work in 14 days, then how long will 8 men and 16 women take to finish the work ?

    A9 days
    B10 days
    C12 days
    D14 days
  • Question 1 - Select One

    If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A4 days
    B5 days
    C3 days
    D2 days
  • Question 1 - Select One

    4 men & 18 women can do a piece of work in 2.5 days, then in how many days 12 woment can complete the same piece of work ?
    A. Ratio of efficiency of men to woment is 3:2.
    B. 6 men & 6 women can complete the dame work in 4 days.

    AStatement A alone is sufficient to answer the question but statement B alone is not sufficient to answer the questions.
    BStatement B alone is sufficient to answer the question but statement A alone is not sufficient to answer the question.
    CBoth the statements taken together are necessary to answer the questions, but neither of the statements alone is sufficient to answer the question.
    DEither stetement A or stetement B by itself is sufficient to answer the question.
  • Question 1 - Select One

    Four men and 6 women can complete a certain piece of work in 5 days whereas three men and 4 women can complete it in 7 days. How many men should assist 25 women to complete times the same work in 5 days?

    A10
    B4
    C8
    D5
  • Question 1 - Select One

    If 4 men or 6 women can do a piece of work in 12 days workIng 7 hours a day, how many days will it take to complete a work twice as large with 10 men and 3 women working together 8 hours a day?

    A6 days
    B7 days
    C8 days
    D10 days
  • Question 1 - Select One

    If 16 men or 20 women can do a piece of work in 25 days, in what time will 28 men and 15 women do it ?

    A1427 days
    B3313 days
    C1834 days
    D10 days

Similar Questions