Doubtnut Promotions Sticky

A 12 HP motor has to be operated 8 hours / day . How much will it cost at the rate of 50 paisa / kWh in 10 days

A

Rs 350/-

B

Rs.358/-

C

Rs.375/-

D

Rs.397/-

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to calculate the total cost of operating a 12 HP motor for 8 hours a day over 10 days, given the cost of electricity is 50 paisa per kWh.

1. Convert Horsepower to Kilowatts:
- We know that 1 HP (Horsepower) is equivalent to 746 Watts.
- Therefore, to convert 12 HP to kilowatts:
Power (in kW)=12HP×746W/HP=8952W
- Since 1 kW = 1000 W, we convert watts to kilowatts:
Power (in kW)=8952W1000=8.952kW9kW

2. Calculate Total Operating Hours:
- The motor operates for 8 hours a day for 10 days:
Total hours=8hours/day×10days=80hours

3. Calculate Total Energy Consumption:
- The total energy consumed in kilowatt-hours (kWh) is given by:
Total energy (in kWh)=Power (in kW)×Total hours
Total energy=9kW×80hours=720kWh

4. Calculate Total Cost:
- The cost of electricity is 50 paisa per kWh, which is equivalent to 0.50 rupees per kWh.
- Therefore, the total cost can be calculated as:
Total cost=Total energy (in kWh)×Cost per kWh
Total cost=720kWh×0.50rupees/kWh=360rupees

Final Answer:
The total cost of operating the motor for 10 days is 360 rupees.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:

    Aa. 30
    Bb. 32
    Cc. 34
    Dd. 36
  • Question 2 - Select One

    A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411
  • Question 3 - Select One

    A can do a piece of work in 6 days working 8 hours a day while B can do the same work in 4 days working 10 hours a day. If the work has to be completed in 5 days, so how many hours do they need to work together in a days?

    A4
    B5411
    C6411
    D4411