In above question, the work done in the two wire is

A

0.5 J, 0.03 J

B

0.25 J, 0 J

C

0.03 J, 0.25 J

D

0J, 0j

Text Solution
Verified by Experts

The correct Answer is:a


As work done, W=F2I2(πD24)y
Where, Y,I and F are constants.
W1D2 or W1W2=D22D21=16
Now, W1=12×103×1×103=0.5J
W2=12×103×10316=132=0.03125
w1W2=0.50.3125=16

Updated on:21/07/2023
Doubtnut Promotions Banner
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • In the above question, if the work done on the system along the curved path 'ba' is 52J, heta abosrbed is

    A140J
    B172J
    C140J
    D172J
  • In the indicator diagram shown,
    ocr_image In the above question, the work done along path CA is –

    A20 joule
    B20 joule
    C30 joule
    Dzero
  • Two wires of same diameter of the same material having the length l and 2l.If the force F is applied on each, the ratio of the work done in the two wires will be

    A1:2
    B1:4
    C2:1
    D1:1