Doubtnut Promotions Sticky

15 men can build a 16.25 -m- long wall up to a certainj height in one day. How many men should be employed to build a wall of the same height but of length 26 metres in one day?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:24 mrn


To solve the problem, we can use the Unitary Method. Here’s the step-by-step solution:

Step 1: Determine the length of the wall that can be built by one man in one day.
We know that 15 men can build a wall of 16.25 meters in one day. To find out how much one man can build in one day, we divide the total length of the wall by the number of men.

Length built by 1 man in 1 day=16.25 m15 men=1.0833 m/man

Step 2: Calculate the total length of the wall to be built.
The length of the new wall is given as 26 meters.

Step 3: Determine how many men are needed to build the 26-meter wall in one day.
Now, we need to find out how many men are required to build a wall of 26 meters in one day. We can use the length that one man can build in one day to find this out.

Number of men required=Total length of the wallLength built by 1 man in 1 day=26 m1.0833 m/man24

Final Answer:
Therefore, approximately 24 men should be employed to build a wall of 26 meters in one day.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 72 men can build a wall of 280 m length in 21 days, how many men could take 18 days to build a similar type of wall of length 100 m?

    A30
    B10
    C18
    D28
  • Question 2 - Select One

    It is given that 16men working 18hr per day can build a wall 36m long, 4m broad and 24m high in 20 days . How many men will be required to build a wall 64 m long 6m broad and 18m high working 12hr per day in 16 days ?

    A60
    B20
    C30
    D35
  • Question 3 - Select One

    20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?

    A10
    B12
    C15
    D20