2 men and 3 women can do a piece of work in 16 days . In how many days can 4 men and 6 women do the same work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:8 days


To solve the problem, we will follow these steps:

Step 1: Define the work done by men and women
Let the work done by one man in one day be M and the work done by one woman in one day be W.

Step 2: Calculate the total work done by 2 men and 3 women in one day
The work done by 2 men in one day is:
2M
The work done by 3 women in one day is:
3W
Thus, the total work done by 2 men and 3 women in one day is:
2M+3W

Step 3: Calculate the total work done in 16 days
Since 2 men and 3 women can complete the work in 16 days, the total work T can be expressed as:
T=(2M+3W)×16

Step 4: Calculate the work done by 4 men and 6 women in one day
Now, we need to find out how much work is done by 4 men and 6 women in one day. The work done by 4 men in one day is:
4M
The work done by 6 women in one day is:
6W
Thus, the total work done by 4 men and 6 women in one day is:
4M+6W

Step 5: Set up the equation for the total work
Let X be the number of days required for 4 men and 6 women to complete the work. The total work can also be expressed as:
T=(4M+6W)×X

Step 6: Equate the two expressions for total work
Now we can equate the two expressions for total work:
(2M+3W)×16=(4M+6W)×X

Step 7: Simplify the equation
We can simplify the equation:
16(2M+3W)=X(4M+6W)
Dividing both sides by 2:
8(2M+3W)=X(4M+6W)

Step 8: Cancel out common terms
Now we can cancel 2M+3W from both sides (assuming it's not zero):
8=X2

Step 9: Solve for X
Now, divide both sides by 2:
X=4

Conclusion
Thus, the number of days required for 4 men and 6 women to complete the work is:
8

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A4 days
    B5 days
    C3 days
    D2 days
  • If 3 men or 6 women can do a piece of work in 16 days, in how many days can 12 men and 8 women do the same piece of work?

    A4 days
    B5 days
    C3 days
    D2 days
  • When 6 men and 8 women can do a piece of work in 15 days, then 11 men and 16 women can do the same work in 8 days. In how many days can 4 men and 4 women do the work ?

    A28
    B24
    C26
    D30