2 men and 5 boys together can finish a piece of work in 4 days, while 3 men and 6 boys can finish it in 3 days. Find the time taken by 1 man alone to finish the work and than taken by 1 boy alone.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:1 man finish in 18 days and 1 boy in 36 days.


To solve the problem, we need to set up equations based on the information provided. Let's break it down step by step.

Step 1: Define Variables
Let:
- X = the number of days one man alone can finish the work.
- Y = the number of days one boy alone can finish the work.

Step 2: Express Work Done in One Day
The work done by one man in one day is 1X and the work done by one boy in one day is 1Y.

Step 3: Set Up the First Equation
According to the problem, 2 men and 5 boys can finish the work in 4 days. Therefore, their combined work in one day is:
2×1X+5×1Y=14
This simplifies to:
2X+5Y=14(1)

Step 4: Set Up the Second Equation
Similarly, for 3 men and 6 boys who can finish the work in 3 days, we have:
3×1X+6×1Y=13
This simplifies to:
3X+6Y=13(2)

Step 5: Clear the Fractions
To eliminate the fractions, we can multiply both sides of equation (1) by 4XY:
4Y2+4X5=XY
This gives us:
8Y+20X=XY(3)

Now, multiply both sides of equation (2) by 3XY:
3Y3+3X6=XY
This gives us:
9Y+18X=XY(4)

Step 6: Rearranging the Equations
From equations (3) and (4), we can rearrange them:
XY8Y20X=0(5)
XY9Y18X=0(6)

Step 7: Subtract the Equations
Now, subtract equation (6) from equation (5):
(XY8Y20X)(XY9Y18X)=0
This simplifies to:
Y2X=0
Thus, we have:
Y=2X(7)

Step 8: Substitute Back
Substituting Y=2X into equation (3):
8(2X)+20X=X(2X)
This simplifies to:
16X+20X=2X2
36X=2X2
Dividing both sides by 2X (assuming X0):
18=X
So, X=18.

Step 9: Find Y
Using equation (7):
Y=2X=2×18=36

Conclusion
Thus, the time taken by one man alone to finish the work is 18 days, and the time taken by one boy alone to finish the work is 36 days.

|


Topper's Solved these Questions


Similar Questions