2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to determine how long it would take for one man and one boy to complete the work. Let's break it down step by step.

Step 1: Define Variables
Let:
- x = number of days one man takes to complete the work.
- y = number of days one boy takes to complete the work.

Step 2: Determine Work Rates
The work done by one man in one day is 1x.
The work done by one boy in one day is 1y.

Step 3: Set Up Equations
From the problem, we have two scenarios:

1. Scenario 1: 2 men and 7 boys can complete the work in 4 days.
2(1x)+7(1y)=14
This simplifies to:
2x+7y=14(Equation 1)

2. Scenario 2: 4 men and 4 boys can complete the work in 3 days.
4(1x)+4(1y)=13
This simplifies to:
4x+4y=13(Equation 2)

Step 4: Clear Fractions
To eliminate the fractions, we can multiply both equations by the least common multiple of the denominators.

For Equation 1, multiply by 4xy:
4y2+4x7=xy
This gives:
8y+28x=xy(Equation 3)

For Equation 2, multiply by 3xy:
3y4+3x4=xy
This gives:
12y+12x=xy(Equation 4)

Step 5: Rearrange Equations
Rearranging Equations 3 and 4 gives:
xy8y28x=0(Equation 3)
xy12y12x=0(Equation 4)

Step 6: Subtract Equations
Now, subtract Equation 4 from Equation 3:
(xy8y28x)(xy12y12x)=0
This simplifies to:
4y16x=0
Thus, we have:
y=4x(Equation 5)

Step 7: Substitute Back
Substituting Equation 5 into Equation 1:
2x+74x=14
Multiplying through by 4x gives:
8+7=x
Thus:
x=15

Step 8: Find y
Using Equation 5:
y=415=60

Step 9: Calculate Work Rate of One Man and One Boy
The work done by one man and one boy in one day is:
1x+1y=115+160
Finding a common denominator (60):
460+160=560=112

Step 10: Calculate Total Time for One Man and One Boy
If one man and one boy together can do 112 of the work in one day, they will complete the work in:
12 days

Final Answer
It would take one man and one boy 12 days to complete the work.

---

|


Topper's Solved these Questions


Similar Questions