2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?
To solve the problem, we need to determine how long it would take for one man and one boy to complete the work. Let's break it down step by step.
Step 1: Define Variables
Let:
- x = number of days one man takes to complete the work.
- y = number of days one boy takes to complete the work.
Step 2: Determine Work Rates
The work done by one man in one day is 1x.
The work done by one boy in one day is 1y.
Step 3: Set Up Equations
From the problem, we have two scenarios:
1. Scenario 1: 2 men and 7 boys can complete the work in 4 days.
2(1x)+7(1y)=14
This simplifies to:
2x+7y=14(Equation 1)
2. Scenario 2: 4 men and 4 boys can complete the work in 3 days.
4(1x)+4(1y)=13
This simplifies to:
4x+4y=13(Equation 2)
Step 4: Clear Fractions
To eliminate the fractions, we can multiply both equations by the least common multiple of the denominators.
For Equation 1, multiply by 4xy:
4y⋅2+4x⋅7=xy
This gives:
8y+28x=xy(Equation 3)
For Equation 2, multiply by 3xy:
3y⋅4+3x⋅4=xy
This gives:
12y+12x=xy(Equation 4)
Step 5: Rearrange Equations
Rearranging Equations 3 and 4 gives:
xy−8y−28x=0(Equation 3)
xy−12y−12x=0(Equation 4)
Step 6: Subtract Equations
Now, subtract Equation 4 from Equation 3:
(xy−8y−28x)−(xy−12y−12x)=0
This simplifies to:
4y−16x=0
Thus, we have:
y=4x(Equation 5)
Step 7: Substitute Back
Substituting Equation 5 into Equation 1:
2x+74x=14
Multiplying through by 4x gives:
8+7=x
Thus:
x=15
Step 8: Find y
Using Equation 5:
y=4⋅15=60
Step 9: Calculate Work Rate of One Man and One Boy
The work done by one man and one boy in one day is:
1x+1y=115+160
Finding a common denominator (60):
460+160=560=112
Step 10: Calculate Total Time for One Man and One Boy
If one man and one boy together can do 112 of the work in one day, they will complete the work in:
12 days
Final Answer
It would take one man and one boy 12 days to complete the work.
---
Let:
- x = number of days one man takes to complete the work.
- y = number of days one boy takes to complete the work.
The work done by one man in one day is 1x.
The work done by one boy in one day is 1y.
From the problem, we have two scenarios:
2(1x)+7(1y)=14
This simplifies to:
2x+7y=14(Equation 1)
4(1x)+4(1y)=13
This simplifies to:
4x+4y=13(Equation 2)
To eliminate the fractions, we can multiply both equations by the least common multiple of the denominators.
4y⋅2+4x⋅7=xy
This gives:
8y+28x=xy(Equation 3)
3y⋅4+3x⋅4=xy
This gives:
12y+12x=xy(Equation 4)
Rearranging Equations 3 and 4 gives:
xy−8y−28x=0(Equation 3)
xy−12y−12x=0(Equation 4)
Now, subtract Equation 4 from Equation 3:
(xy−8y−28x)−(xy−12y−12x)=0
This simplifies to:
4y−16x=0
Thus, we have:
y=4x(Equation 5)
Substituting Equation 5 into Equation 1:
2x+74x=14
Multiplying through by 4x gives:
8+7=x
Thus:
x=15
Using Equation 5:
y=4⋅15=60
The work done by one man and one boy in one day is:
1x+1y=115+160
Finding a common denominator (60):
460+160=560=112
If one man and one boy together can do 112 of the work in one day, they will complete the work in:
12 days
It would take one man and one boy 12 days to complete the work.
Topper's Solved these Questions
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - LINEAR EQUATIONS IN TWO VARIABLES EXERCISE - Exercise 3a18videos
LINEAR EQUATIONS IN TWO VARIABLES
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - LINEAR EQUATIONS IN TWO VARIABLES EXERCISE - Exercise 3A8videos
LINEAR EQUATIONS IN TWO VARIABLES
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - INTRODUCTION TO TRIGONOMETRYEXERCISE - Revision Exercise Long Answer Questions5videos
INTRODUCTION TO TRIGONOMETRY
- BOOK - NAGEEN PRAKASHAN ENGLISHCHAPTER - POLYNOMIALSEXERCISE - Revision Exercise Long Answer Questions4videos
POLYNOMIALS
Similar Questions
Rakesh can do piece of work in 20 days. How much work can be do in 4 days?
View SolutionIf 56 men can do a piece of work in 42 days. How many men will do it in 14 days?
View Solution3 men and 4 boys can do a piece of work in 14 days, while 4 men and 6 boys can do it in 10 days. How long would it take 1 boy to finish the work?
View Solution6 men and 8 boys can do a piece of work in 7 days, while 8 men and 12 boys do the same work in 5 days. How long would it take one boy to finish the same work?
View Solution36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
How long will it take them to do the work, working together ?View SolutionIf 12 men and 16 boys can do a piece of work in 5 days and, 13 men and 24 boys can do it in 4 days, how long will 7 men and 10 boys take to do it ?
View Solution8 men and 12 boys can finish a piece of work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.
View SolutionIf 52 men can do a piece of work in 35 days in how many days 28 men will do it ?
View Solution2 men or 3 women can do a piece of work in 45 days. Find, in how many days will 6 men and 1 woman be able to complete the same work ?
View Solution