Doubtnut Promotions Sticky

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:65 men


To solve the problem step by step, we can use the concept of inverse proportion. Here's how we can find the number of men needed to finish the work in 16 days:

Step 1: Understand the relationship
We know that if more men are working, the number of days required to finish the work decreases. This indicates an inverse relationship between the number of men and the number of days.

Step 2: Set up the known values
From the problem, we have:
- x1=40 men
- y1=26 days
- y2=16 days (the new number of days we want to finish the work)
- x2=? (the number of men we need to find)

Step 3: Use the inverse proportion formula
According to the inverse proportion rule:
x1×y1=x2×y2
Substituting the known values into the equation:
40×26=x2×16

Step 4: Solve for x2
First, calculate 40×26:
40×26=1040
Now we have:
1040=x2×16
To find x2, divide both sides by 16:
x2=104016

Step 5: Perform the division
Calculating 104016:
x2=65

Conclusion
Therefore, the number of men needed to finish the work in 16 days is 65 men.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

    A52
    B31
    C13
    D65
  • Question 2 - Select One

    10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?

    A2
    B4
    C5
    D11
  • Question 3 - Select One

    If 300 men can do a piece of work in 16 days. How many men would do (1/5) of the work in 15 days ?

    A56
    B64
    C60
    D72