8 men and 12 boys can finish a work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:Time taken by one man alone= 140 days and
time taken by one boy alone = 280 days

Updated on:21/07/2023
|
Answer

Step by step video, text & image solution for 8 men and 12 boys can finish a work in 10 days while 6 men and 8 boys can finish it in 14 days. Find the time taken by one man alone and that by one boy alone to finish the work. by Maths experts to help you in doubts & scoring excellent marks in Class 10 exams.

Updated on:21/07/2023


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • If 14 men and 12 boys can finish work in 4 days , while 8 men and 16 boys can finish the same work in 5 days . Compare the 1 day work of 1 man and 1 boy .

    A2
    B112
    C12
    D3