A and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job ?
To solve the problem step by step, we will first define the work done by each pair of workers and then derive the time taken by A alone to complete the work.
1. Define the Work Done by Each Pair:
- A and B can complete the work in 12 days. Therefore, the work done by A and B in one day is:
Work done by A and B in one day=112
- B and C can complete the work in 15 days. Therefore, the work done by B and C in one day is:
Work done by B and C in one day=115
- C and A can complete the work in 20 days. Therefore, the work done by C and A in one day is:
Work done by C and A in one day=120
2. Set Up the Equations:
- Let the work done by A in one day be A, by B be B, and by C be C. We can write the following equations based on the work done:
A+B=112(Equation 1)
B+C=115(Equation 2)
C+A=120(Equation 3)
3. Add the Equations:
- Adding all three equations gives:
(A+B)+(B+C)+(C+A)=112+115+120
- This simplifies to:
2A+2B+2C=112+115+120
4. Calculate the Right Side:
- To add the fractions on the right side, we need a common denominator. The least common multiple (LCM) of 12, 15, and 20 is 60.
- Converting each fraction:
112=560,115=460,120=360
- Adding these gives:
560+460+360=1260=15
5. Simplify the Equation:
- Thus, we have:
2A+2B+2C=15
- Dividing everything by 2:
A+B+C=110(Equation 4)
6. Find A's Work Alone:
- Now, we can find A's work alone by subtracting Equation 2 from Equation 4:
(A+B+C)−(B+C)=110−115
- This simplifies to:
A=110−115
7. Calculate the Right Side:
- To subtract these fractions, we need a common denominator. The LCM of 10 and 15 is 30.
- Converting each fraction:
110=330,115=230
- Thus:
A=330−230=130
8. Conclusion:
- This means A can complete the work alone in:
Time taken by A=30 days
Final Answer:
A alone will take 30 days to finish the job.
- A and B can complete the work in 12 days. Therefore, the work done by A and B in one day is:
Work done by A and B in one day=112
- B and C can complete the work in 15 days. Therefore, the work done by B and C in one day is:
Work done by B and C in one day=115
- C and A can complete the work in 20 days. Therefore, the work done by C and A in one day is:
Work done by C and A in one day=120
- Let the work done by A in one day be A, by B be B, and by C be C. We can write the following equations based on the work done:
A+B=112(Equation 1)
B+C=115(Equation 2)
C+A=120(Equation 3)
- Adding all three equations gives:
(A+B)+(B+C)+(C+A)=112+115+120
- This simplifies to:
2A+2B+2C=112+115+120
- To add the fractions on the right side, we need a common denominator. The least common multiple (LCM) of 12, 15, and 20 is 60.
- Converting each fraction:
112=560,115=460,120=360
- Adding these gives:
560+460+360=1260=15
- Thus, we have:
2A+2B+2C=15
- Dividing everything by 2:
A+B+C=110(Equation 4)
- Now, we can find A's work alone by subtracting Equation 2 from Equation 4:
(A+B+C)−(B+C)=110−115
- This simplifies to:
A=110−115
- To subtract these fractions, we need a common denominator. The LCM of 10 and 15 is 30.
- Converting each fraction:
110=330,115=230
- Thus:
A=330−230=130
- This means A can complete the work alone in:
Time taken by A=30 days
A alone will take 30 days to finish the job.
Topper's Solved these Questions
Similar Questions
A and B can finish a piece of work in 12 days, B and C in 15 days shile C and A in 20 days. How long will they take to finish it together ? How long will each take to finish the work alone ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
How long will it take them to do the work, working together ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?
View SolutionA and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View SolutionA and B can do a piece of work in 18 days .B and C in 24 days and A and C in 36 days .In what time can they do it , all works together
View SolutionA can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
View SolutionA and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together ?
View Solution3 men and 4 boys can do a piece of work in 14 days, while 4 men and 6 boys can do it in 10 days. How long would it take 1 boy to finish the work?
View SolutionA, B and C can do a piece of work in 6 days, 12 days and 24 days respectively. In what time will they altogether do it ?
View SolutionA can do a piece of work in 24 days, A and B can do it in 16 days and A,B and C in 1023 days. In how many days can A and C do it working together ?
View Solution