A and B can do a piece of work in 18 days .B and C in 24 days and A and C in 36 days .In what time can they do it , all works together
To solve the problem step by step, we will first determine the work done by each pair of workers and then find the combined work rate of A, B, and C.
Step 1: Determine the work rates of the pairs
- A and B can complete the work in 18 days. Therefore, their combined work rate is:
Work rate of A + B=118 (work done in one day)
- B and C can complete the work in 24 days. Therefore, their combined work rate is:
Work rate of B + C=124 (work done in one day)
- A and C can complete the work in 36 days. Therefore, their combined work rate is:
Work rate of A + C=136 (work done in one day)
Step 2: Set up the equations
From the above information, we have three equations:
1. A+B=118
2. B+C=124
3. A+C=136
Step 3: Add the equations
Now, we will add all three equations together:
(A+B)+(B+C)+(A+C)=118+124+136
This simplifies to:
2A+2B+2C=118+124+136
Step 4: Calculate the right-hand side
To add the fractions on the right-hand side, we need to find the least common multiple (LCM) of 18, 24, and 36. The LCM is 72.
Now we convert each fraction:
- 118=472
- 124=372
- 136=272
Adding these together:
472+372+272=972=18
Step 5: Solve for A + B + C
Now we have:
2A+2B+2C=18
Dividing both sides by 2 gives:
A+B+C=116
Step 6: Calculate the time taken for A, B, and C to complete the work together
The combined work rate of A, B, and C is 116 of the work done in one day. Therefore, the time taken to complete the work when all three work together is:
Time=1Work rate=1116=16 days
Final Answer
A, B, and C can complete the work together in 16 days.
---
- A and B can complete the work in 18 days. Therefore, their combined work rate is:
Work rate of A + B=118 (work done in one day)
Work rate of B + C=124 (work done in one day)
Work rate of A + C=136 (work done in one day)
From the above information, we have three equations:
1. A+B=118
2. B+C=124
3. A+C=136
Now, we will add all three equations together:
(A+B)+(B+C)+(A+C)=118+124+136
2A+2B+2C=118+124+136
To add the fractions on the right-hand side, we need to find the least common multiple (LCM) of 18, 24, and 36. The LCM is 72.
- 118=472
- 124=372
- 136=272
472+372+272=972=18
Now we have:
2A+2B+2C=18
Dividing both sides by 2 gives:
A+B+C=116
The combined work rate of A, B, and C is 116 of the work done in one day. Therefore, the time taken to complete the work when all three work together is:
Time=1Work rate=1116=16 days
A, B, and C can complete the work together in 16 days.
Topper's Solved these Questions
Similar Questions
A and B can do a work in 8 days, B and C in 12 days, and A and C in 16 days. In what time can they do it, all working together ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
In what time can each finish it working alone ?
View SolutionA can do a piece of work in 10 days, B in 18 days and A, B and C together in 4 days. In what time would C do it alone ?
View SolutionA and B can do a piece of work in 40 days, B and C in 30 days, and C and A in 24 days.
How long will it take them to do the work, working together ?
View SolutionA and B can do a piece of work in 12 days, B and C in 15 days, and C and A in 20 days. How much time will A alone take to finish the job ?
View SolutionA and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View SolutionA and B can finish a piece of work in 12 days, B and C in 15 days shile C and A in 20 days. How long will they take to finish it together ? How long will each take to finish the work alone ?
View SolutionA can do a piece of work in 24 days, A and B can do it in 16 days and A,B and C in 1023 days. In how many days can A and C do it working together ?
View SolutionA, B and C can do a piece of work in 6 days, 12 days and 24 days respectively. In what time will they altogether do it ?
View SolutionAmit can do a piece of work in 4 days and Sumit can do it in 6 days How long will they take, if both Amit and Sumit work together ?
View Solution