A and B can finish a work in 20 days . A alone can do of the work in 12 days.In how many days can B alone do it?
To solve the problem step by step, we will follow the information given in the question and calculate the required values.
1. Understanding the Work Done by A and B Together:
- A and B can finish the work in 20 days.
- Therefore, in one day, A and B together can do:
Work done by A and B in one day=120
2. Understanding the Work Done by A Alone:
- A can do 15 of the work in 12 days.
- This means A’s work in one day is:
Work done by A in one day=15×12=160
3. Calculating the Work Done by B Alone:
- Let the work done by B in one day be b.
- From the information above, we know:
Work done by A and B in one day=Work done by A in one day+Work done by B in one day
- Substituting the values we have:
120=160+b
4. Finding B's Work:
- To find b, we need to isolate it:
b=120−160
- To subtract these fractions, we need a common denominator. The least common multiple (LCM) of 20 and 60 is 60.
- Rewriting 120 with a denominator of 60:
120=360
- Now, substituting back:
b=360−160=260=130
5. Calculating the Days B Takes to Complete the Work:
- If B can do 130 of the work in one day, then the total number of days B will take to finish the work alone is:
Days taken by B=1130=30 days
Final Answer:
B alone can finish the work in 30 days.
- A and B can finish the work in 20 days.
- Therefore, in one day, A and B together can do:
Work done by A and B in one day=120
- A can do 15 of the work in 12 days.
- This means A’s work in one day is:
Work done by A in one day=15×12=160
- Let the work done by B in one day be b.
- From the information above, we know:
Work done by A and B in one day=Work done by A in one day+Work done by B in one day
- Substituting the values we have:
120=160+b
- To find b, we need to isolate it:
b=120−160
- To subtract these fractions, we need a common denominator. The least common multiple (LCM) of 20 and 60 is 60.
- Rewriting 120 with a denominator of 60:
120=360
- Now, substituting back:
b=360−160=260=130
- If B can do 130 of the work in one day, then the total number of days B will take to finish the work alone is:
Days taken by B=1130=30 days
B alone can finish the work in 30 days.
Topper's Solved these Questions
Similar Questions
A and B can polish the floors of a building in 10 days. A alone can do 14 of work in 12 days. In how many days can B alone polish the floor?
View SolutionA and B can polish the floors of a building in 25 days. A alone can do 13 of this job in 15 days. In how many days can B alone polish the floors of the building?
View SolutionIf 12 women can do a piece of work in 9 days, in how many days can 18 women do it ?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf 52 men can do a piece of work in 35 days in how many days 28 men will do it ?
View SolutionA can do 13 of a certain work in 12 days and B can do 16 of the same work in 4 days. Find, in how many days will they together complete the work ?
View SolutionA can do a piece of work in 24 days, A and B can do it in 16 days and A,B and C in 1023 days. In how many days can A and C do it working together ?
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
C alone,
View SolutionA and B complete a piece of work in 24 days, B and C do the same work in 36 days, and A, B and C together finish it in 18 days. In how many days will :
A alone,
View SolutionA and B can do piece of work in 12 days; B and C in 15 days; C and A in 20 days. In how many days will they finish it together and separately ?
View Solution