A and B can finish a work in 20 days . A alone can do 1 5 t h of the work in 12 days.In how many days can B alone do it?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, we will follow the information given in the question and calculate the required values.

1. Understanding the Work Done by A and B Together:
- A and B can finish the work in 20 days.
- Therefore, in one day, A and B together can do:
Work done by A and B in one day=120

2. Understanding the Work Done by A Alone:
- A can do 15 of the work in 12 days.
- This means A’s work in one day is:
Work done by A in one day=15×12=160

3. Calculating the Work Done by B Alone:
- Let the work done by B in one day be b.
- From the information above, we know:
Work done by A and B in one day=Work done by A in one day+Work done by B in one day
- Substituting the values we have:
120=160+b

4. Finding B's Work:
- To find b, we need to isolate it:
b=120160
- To subtract these fractions, we need a common denominator. The least common multiple (LCM) of 20 and 60 is 60.
- Rewriting 120 with a denominator of 60:
120=360
- Now, substituting back:
b=360160=260=130

5. Calculating the Days B Takes to Complete the Work:
- If B can do 130 of the work in one day, then the total number of days B will take to finish the work alone is:
Days taken by B=1130=30 days

Final Answer:
B alone can finish the work in 30 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions