Doubtnut Promotions Sticky

A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. In how many days can A alone finish the work?

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:20 days


To solve the problem, we will follow these steps:

Step 1: Understand the Work Rates
A and B together can complete the work in 12 days. This means that their combined work rate is:
Work rate of A + B=1 work12 days=112

B alone can complete the work in 30 days, so B's work rate is:
Work rate of B=1 work30 days=130

Step 2: Calculate A's Work Rate
To find A's work rate, we can use the relationship:
Work rate of A=Work rate of A + BWork rate of B
Substituting the known values:
Work rate of A=112130

Step 3: Find a Common Denominator
To perform the subtraction, we need a common denominator. The least common multiple (LCM) of 12 and 30 is 60. Now we can rewrite the fractions:
112=560and130=260
Now substitute these back into the equation:
Work rate of A=560260=360

Step 4: Simplify A's Work Rate
Now simplify 360:
Work rate of A=120

Step 5: Calculate Time Taken by A Alone
If A can do 120 of the work in one day, then the time taken by A to finish the entire work is the reciprocal of the work rate:
Time taken by A=1120=20 days

Final Answer
A alone can finish the work in 20 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A and B together can do a job in 12 days. B alone can finish it in 28 days. In how many days can A alone finish the work?
    (a)21 days
    (b)19 days
    (c)20 days
    (d)none of these

    A21 days
    B19 days
    C20 days
    DNone of these
  • Question 2 - Select One

    A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A15 days
    B18 days
    C20 days
    D25 days
  • Question 3 - Select One

    A and B together can do a piece of work in 12 days, while B alone can finish it in 30 days. A alone can finish the work in

    A20 days
    B25 days
    C15 days
    D18 days