A, B, C can do a work in 12, 8, 32 days respectively. They start working together but after 5 days A quit himself and B quit himself 4 days before the completion of the work. In how many days was the work completed?
6415 days
61415 days
5415 days
51415 days
The correct Answer is:B
To solve the problem step by step, we need to calculate the total work done by A, B, and C, and how their individual contributions affect the overall completion of the work.
1. Determine the Work Rate of A, B, and C:
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 32 days, so C's work rate is 132 of the work per day.
2. Calculate the Total Work Done Together in the First 5 Days:
- In the first 5 days, A, B, and C work together:
Total work done in 5 days=5(112+18+132)
- To add these fractions, find a common denominator. The least common multiple of 12, 8, and 32 is 96.
112=896,18=1296,132=396
- Therefore,
112+18+132=8+12+396=2396
- Now calculate the total work done in 5 days:
Total work done=5×2396=11596
3. Determine the Remaining Work After 5 Days:
- The total work is considered as 1 (or 96/96). The remaining work after 5 days is:
Remaining work=1−11596=96−11596=−1996
- Since this is incorrect, we need to recalculate the remaining work:
Remaining work=1−11596=96−11596=1996
4. Calculate the Work Done by B and C After A Quits:
- After 5 days, A quits. B continues working until 4 days before the work is completed.
- Let x be the total number of days taken to complete the work. Then B works for x−4 days and C works for x days.
- The work done by B in x−4 days is:
Work by B=(x−4)×18
- The work done by C in x days is:
Work by C=x×132
5. Set Up the Equation for Total Work:
- The total work done by B and C after A quits must equal the remaining work:
11596+(x−4)×18+x×132=1
6. Combine and Solve the Equation:
- Substitute the remaining work:
(x−4)×18+x×132=1−11596
- Convert everything to a common denominator and solve for x.
7. Final Calculation:
- After simplifying, we find:
x=10415≈6.93 days
- This means the work was completed in approximately 61415 days.
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 32 days, so C's work rate is 132 of the work per day.
- In the first 5 days, A, B, and C work together:
Total work done in 5 days=5(112+18+132)
- To add these fractions, find a common denominator. The least common multiple of 12, 8, and 32 is 96.
112=896,18=1296,132=396
- Therefore,
112+18+132=8+12+396=2396
- Now calculate the total work done in 5 days:
Total work done=5×2396=11596
- The total work is considered as 1 (or 96/96). The remaining work after 5 days is:
Remaining work=1−11596=96−11596=−1996
- Since this is incorrect, we need to recalculate the remaining work:
Remaining work=1−11596=96−11596=1996
- After 5 days, A quits. B continues working until 4 days before the work is completed.
- Let x be the total number of days taken to complete the work. Then B works for x−4 days and C works for x days.
- The work done by B in x−4 days is:
Work by B=(x−4)×18
- The work done by C in x days is:
Work by C=x×132
- The total work done by B and C after A quits must equal the remaining work:
11596+(x−4)×18+x×132=1
- Substitute the remaining work:
(x−4)×18+x×132=1−11596
- Convert everything to a common denominator and solve for x.
- After simplifying, we find:
x=10415≈6.93 days
- This means the work was completed in approximately 61415 days.
Topper's Solved these Questions
- IMO QUESTION PAPER 2020 SET 1BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2020 SET 1EXERCISE - Achievers Section
5 Videos
- IMO QUESTION PAPER 2020 SET 1BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2020 SET 1EXERCISE - Achievers Section
5 Videos
- IMO QUESTION PAPER 2019 SET BBOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2019 SET BEXERCISE - ACHIEVERS SECTION
5 Videos
- IMO QUESTION PAPER 2020 SET 2 BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER 2020 SET 2 EXERCISE - Achievers Section
4 Videos
Similar Questions
A, B and C can complete a work in 10, 12 and 15 days respectively. They started the work together. But A left the work 5 days before its completion. B also left the work 2 days after A left. In how many days was the work completed?
a.4
b. 15
c. 7
d. 8
View SolutionA, B and C can finish a piece of work in 12 days, 15 days and 20 days respectively. They started working together. B left the work after working 3 days and C left the work 3 days before completion of the work. In how many days work will be finished?
View Solution
Knowledge Check
A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?
A9 daysB15 daysC12 daysD14 daysA, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B1025C10730Dnone of theseA, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?
A7310B10215C10730Dnone of these
A, B and C can complete a piece of work in 25, 30 and 50 days. Respectively. They started the work together But A and C left 2 days before the completion of the work. In how many days will the work is completed ?
View SolutionA, B and C can complete a work separately in 24, 36 and 48 days respectively. They started together but C left after 4 days of start and A left 3 days before the completion of work. In how many days will the work be completed?
View SolutionA, B and C can do a work separately in 16, 32 and 48 days respectively. They started the work together but B leaving off 8 days and C six days beofre the completion of the work. In what time is the work finished?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View SolutionA,B andC can complete a piece of work in 6,12 and 18 days respectively. A and B started the work and C joined them after one day. B left just 2 days before the completion of the whole work.In how many days was the work completed?
View Solution