Doubtnut Promotions Sticky

A, B, C can do a work in 12, 8, 32 days respectively. They start working together but after 5 days A quit himself and B quit himself 4 days before the completion of the work. In how many days was the work completed?

A

6415 days

B

61415 days

C

5415 days

D

51415 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, we need to calculate the total work done by A, B, and C, and how their individual contributions affect the overall completion of the work.

1. Determine the Work Rate of A, B, and C:
- A can complete the work in 12 days, so A's work rate is 112 of the work per day.
- B can complete the work in 8 days, so B's work rate is 18 of the work per day.
- C can complete the work in 32 days, so C's work rate is 132 of the work per day.

2. Calculate the Total Work Done Together in the First 5 Days:
- In the first 5 days, A, B, and C work together:
Total work done in 5 days=5(112+18+132)
- To add these fractions, find a common denominator. The least common multiple of 12, 8, and 32 is 96.
112=896,18=1296,132=396
- Therefore,
112+18+132=8+12+396=2396
- Now calculate the total work done in 5 days:
Total work done=5×2396=11596

3. Determine the Remaining Work After 5 Days:
- The total work is considered as 1 (or 96/96). The remaining work after 5 days is:
Remaining work=111596=9611596=1996
- Since this is incorrect, we need to recalculate the remaining work:
Remaining work=111596=9611596=1996

4. Calculate the Work Done by B and C After A Quits:
- After 5 days, A quits. B continues working until 4 days before the work is completed.
- Let x be the total number of days taken to complete the work. Then B works for x4 days and C works for x days.
- The work done by B in x4 days is:
Work by B=(x4)×18
- The work done by C in x days is:
Work by C=x×132

5. Set Up the Equation for Total Work:
- The total work done by B and C after A quits must equal the remaining work:
11596+(x4)×18+x×132=1

6. Combine and Solve the Equation:
- Substitute the remaining work:
(x4)×18+x×132=111596
- Convert everything to a common denominator and solve for x.

7. Final Calculation:
- After simplifying, we find:
x=104156.93 days
- This means the work was completed in approximately 61415 days.

|
Updated on:8/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A, B and C can complete a work in 16, 24 and 32 days, respectively. They started together but C left after 4 days of starting and A left 6 days before completion of the work. In how many days will the work be completed ?

    A9 days
    B15 days
    C12 days
    D14 days
  • Question 2 - Select One

    A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these
  • Question 3 - Select One

    A, B and C can complete a piece of-work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B10215
    C10730
    Dnone of these