A can complete a work in 10 days and B can complete the same work in 15 days. In how many days they together will do the same work?

A

5 days

B

6 days

C

8 days

D

9 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem of how many days A and B will take to complete the work together, we can follow these steps:

Step 1: Determine the work done by A in one day.
A can complete the work in 10 days. Therefore, the work done by A in one day is:
Work done by A in one day=110

Step 2: Determine the work done by B in one day.
B can complete the work in 15 days. Therefore, the work done by B in one day is:
Work done by B in one day=115

Step 3: Calculate the total work done by A and B in one day.
To find out how much work A and B can do together in one day, we add their individual work:
Total work done in one day=Work done by A+Work done by B=110+115

Step 4: Find the LCM of the denominators.
To add the fractions, we need a common denominator. The denominators are 10 and 15. The least common multiple (LCM) of 10 and 15 is 30.

Step 5: Convert the fractions to have the same denominator.
Now we convert both fractions:
110=330(by multiplying numerator and denominator by 3)
115=230(by multiplying numerator and denominator by 2)

Step 6: Add the fractions.
Now we can add the two fractions:
330+230=530

Step 7: Simplify the result.
We can simplify 530 to:
530=16

Step 8: Calculate the total number of days to complete the work together.
If A and B together can do 16 of the work in one day, then the total number of days to complete the work is the reciprocal of 16:
Total days=116=6

Final Answer:
Therefore, A and B together will complete the work in 6 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • X, Y and Z together can complete a work in 20 days. Y and Z can complete the same work in 30 days. In how many days X alone can complete the same work?

    AA)60
    BB)45
    CC)40
    DD)50
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42
  • Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?

    A30
    B50
    C45
    D42