Doubtnut Promotions Sticky

A can do 1 5 th part of the work in 12 days, B can do 60% of the work in 30 days and C can do 1 3 rd of the work in 15 days. Who will complete the work first?

A

A

B

B

C

C

D

A and B both

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To determine who will complete the work first among A, B, and C, we need to calculate the total time each person takes to complete the entire work based on the information given.

1. Calculate the total time for A:
- A can do 15 of the work in 12 days.
- To find the total time A takes to complete the entire work, we multiply the time taken for 15 of the work by 5:
Total time for A=12 days×5=60 days

2. Calculate the total time for B:
- B can do 60% of the work in 30 days.
- First, convert 60% to a fraction: 60%=60100=35.
- To find the total time B takes to complete the entire work, we set up the equation:
Let total work be W.
35W is done in 30 days.
- Therefore, the total work W can be calculated as:
Total time for B=30 days×53=50 days

3. Calculate the total time for C:
- C can do 13 of the work in 15 days.
- To find the total time C takes to complete the entire work, we multiply the time taken for 13 of the work by 3:
Total time for C=15 days×3=45 days

4. Compare the total times:
- A takes 60 days,
- B takes 50 days,
- C takes 45 days.

5. Conclusion:
- The person who completes the work first is C, as C takes the least time (45 days).

Final Answer:
C will complete the work first.

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    P can do (1/4)th of work in 10 days, Q can do 40% of work in 40 days and R can do (1/3)rd of work in 13 days. Who will complete the work first?

    AP
    BQ
    CR
    DBoth P and R
  • Question 2 - Select One

    X can do 14 of a work in 10 days, Y can do 40% of the same work in 40 days and Z can do 13 of the work in 13 days. Who will complete the work first?

    AX
    BY
    CZ
    Dboth X and Z
  • Question 3 - Select One

    A can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in

    A6 days
    B4 days
    C8 days
    D9 days