A' can do a piece of work in 4 days and B in 12 days. In how many days can A and B together complete the same piece of work ?

A

7 days

B

3 days

C

2 days

D

4 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem of how many days A and B can complete a piece of work together, we can follow these steps:

Step 1: Determine the work rates of A and B
- A can complete the work in 4 days. Therefore, A's work rate is:
Work rate of A=1 work4 days=14 work per day

- B can complete the work in 12 days. Therefore, B's work rate is:
Work rate of B=1 work12 days=112 work per day

Step 2: Calculate the combined work rate of A and B
- To find the combined work rate when A and B work together, we add their individual work rates:
Combined work rate=Work rate of A+Work rate of B=14+112

Step 3: Find a common denominator and add the fractions
- The least common multiple (LCM) of 4 and 12 is 12. We can convert 14 to have a denominator of 12:
14=312
- Now we can add the two fractions:
Combined work rate=312+112=412=13 work per day

Step 4: Calculate the time taken to complete the work together
- If A and B together can complete 13 of the work in one day, then the time taken to complete 1 whole work is the reciprocal of their combined work rate:
Time taken=1 work13 work per day=3 days

Final Answer
A and B together can complete the work in 3 days.

---

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?

    A5 days
    B4 days
    C3 days
    D2 days
  • A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A70 days
    B4234 days
    C2717days
    D1717 days
  • If A and B together can complete a piece of work in 15 days and B alone in 20 days, in how many day can A alone complete the work?

    A60 days
    B45 days
    C40 days
    D30 days