Doubtnut Promotions Sticky

A company manufactures bicycles and tricycles, each of which must be processed through two machines A and B. Machine A has maximum of 120 hours available and machine B has a maximum of 180 hours available. Manufacturing a bicycle requires 6 hours on machine A and 3 hours on machine B. Manufacturing a tricycle requires 4 hours on machine A and 10 hours on machine B.
If profits are ₹ 180 for a bicycle and ₹ 220 for a tricycle, determine the number of bicycles and tricycles that should be manufactured in order to maximize the profit.

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

Let x bicycles and y tricycles are to be manufactured. Then the total profit is z=(180x+220y)
This is a linear function which is to be maximized. Hence, it is the objective function. The constraints are as per the following table :
ocr_image
From the table, the constraints are
6x+4y120,3x+10y180
Also, the number of bicycles and tricycles cannot be negative
x0,y0.
Hence, the mathematical formulation of given LPP is :
Maximize z=180x+220y, subject to
6x+4y120,3x+10y180,x0,y0 .
First we draw the lines AB and CD whose equations are 6x+4y=120and3x+10y=180 respectively.
ocr_image
The feasible region is OAPDO which is shaded in the figure.
The vertices of s the feasible region are O(0,0),A(20,0),PandD(0,18).
P is the point of intersection of the lines
3x+10y=180 ...(1)
and 6x+4y=120 ... (2)
Multiplying equation (1) by 2, we get,
6x+20y=360
Subtracting equation (2) from this equation, we get,
16y=240 y=15
from (1),3x+10(15)=180
3x=30 x=10
P=(10,15)
The values of the objective function z=180x+220y at these vertices are
z(O)=180(0)+220(0)=0
z(A)=180(20)+220(0)=3600
z(P)=180(10)+220(15)=1800+3300=5100
z(D)=180(0)+220(18)=3960
the maximum value of z is 5100 at the point (10,15).
Hence, 10 bicycles and 15 tricycles should be manufactured in order to have the maximum profit of ₹ 5100.

|
Updated on:21/07/2023

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    A firm makes pants and shirts . A shirt takes 2 hours on machine and 3 hours of man lobour while a pant takes 3 hours on machine and 2 hours of man labour .In a week , there are 70 hours of machine and 75 hous of man lobour available . If the firm dertermines to make x shirts and y pants per week , then for this linear constraints are

    Ax0,y0,2x+3y70,3x+2y75
    Bx0,y0,2x+3y70,3x+2y75
    Cx0,y0,2x+3y70,3x+2y75
    Dx0,y0,2x+3y70,3x+2y75
  • Question 2 - Select One

    A printing company prints two types of magzines A and B. The company earns Rs. 20 and Rs. 30 on each copy of magazines A and B respectively. The magazine A requires 2 hours on machine I, 4 hours on Machine II and 2 hours machine III. Magazine B requires 3 hours on machine I, 5 hours on machine II and 3 hours on machine III. Machines I,II, III are available for 35, 50 and 70 hours per week respectively. Formulate the LPP to determine weekly production of magazines A and B, so that the total profit is maximum

    AMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
    BMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
    CMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0
    DMaximize z=20x+3y subject to 2x+3y35,4x+5y50,2x+3y70,x0,y0