A man takes the contract of construction work. The probability is 0.30, if there will be no strike. The probability that the construct work will be completed on time are 0.8 and 0.3 in cases of no strike and in case strike respectively. Find the probability that the construction work will be completed in time.

A

0.34

B

0.56

C

0.64

D

0.45

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D


Let E= event that there is no strike.
E'= event that there is strike.
Now P(E)=0.30
P(E')=1P(E)
=10.30
=0.70
Let A= event that the work completed in time.
P(A/E)=0.8 and P(A/E')0.3
P(A)=P(E).P(A/E)+P(E')+P(E').P(A/E')
=0.30×0.8+0.70×0.3
=0.24+0.21
=0.45

|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Shailendra, Amit and Suraj can complete a work in 6, 12 and 15 days respectively. Find the time taken to complete the work if they are working together.

    A60/17 days
    B60/23 days
    C60/19 days
    D60/29 days