By working together, A and B can finish a work in 15 days. If B alone can finish the work in 20 days, in how many days can A alone finish the work?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:60 days


To solve the problem step by step, we will use the concept of work done and the formula for combined work.

1. Understanding the Problem:
- A and B together can complete the work in 15 days.
- B alone can complete the work in 20 days.
- We need to find out how many days A alone would take to complete the work.

2. Setting Up the Variables:
- Let the number of days A alone takes to finish the work be X.
- The work done by A in one day is 1X.
- The work done by B in one day is 120 (since B takes 20 days).

3. Combined Work:
- When A and B work together, they complete the work in 15 days, so their combined work in one day is 115.

4. Setting Up the Equation:
- According to the formula for combined work:
Work done by A in one day+Work done by B in one day=Combined work done in one day
- This can be expressed as:
1X+120=115

5. Finding a Common Denominator:
- The common denominator for X, 20, and 15 is 60X.
- Rewriting the equation:
6060X+3X60X=4X60X
- This simplifies to:
60+3X=4X

6. Solving for X:
- Rearranging the equation gives:
4X3X=60
X=60

7. Conclusion:
- A alone can finish the work in 60 days.

|


Similar Questions


Knowledge Check

  • A and B complete a work in 16 days, while A alone can finish that work in 24 days. In how many days, B alone can finish that work ?

    A56 days
    B48 days
    C36 days
    D64 days
  • P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?

    A813
    B8.5
    C9
    D12
  • 10 men and 15 women finish a work in 6 days. One man alone finishes that work in 100 days. In how many days will a women finish the work ?

    A125 days
    B150 days
    C90 days
    D225 days